Hersey Street construction update

Hersey Street Paving Schedule:
  • Wednesday November 6th – Grind Stage 1 (Lori Lane to Laurel Street) & Pave N. Mountain Avenue Intersection
  • Thursday November 7th – Top lift pave north side of Hersey Street from N. Mountain Avenue to Monarque Health & Wellness Center (148 E Hersey St)
  • Friday November 8th – Top lift pave south side of Hersey Street from N. Mountain Avenue to Oak Street & complete north side to Oak Street
  • Saturday November 9th – Stage 1 subsurface dig-outs/repairs, asphalt pre-leveling and trench patching
  • Monday November 11th – Top lift pave north side of Hersey Street from Oak Street to Lori Lane
  • Tuesday November 12th – Top lift pave south side of Hersey Street from Oak Street to Lori Lane
 
Some warnings and reminders for travel through the work-zone:
  • Hersey Street traffic will flow east to west ONLY, with detours in place to loop around to desired locations
  • Up to 20-minute delays can be expected   
  • Drivers should plan on limited access in and out of businesses and residential driveways
  • While work is occurring in the above areas, no on-street parking will be allowed

Online City Services

UTILITIES-Connect/Disconnect,
Pay your bill & more 
Connect to
Ashland Fiber Network
Request Conservation
Evaluation
Proposals, Bids
& Notifications
Request Building
Inspection
Building Permit
Applications
Apply for Other
Permits & Licenses
Register for
Recreation Programs

©2024 City of Ashland, OR | Site Handcrafted in Ashland, Oregon by Project A

Quicklinks

Connect

Share

twitter facebook Email Share
back to top