City of Ashland - Home
Home Mayor & Council Departments Commissions & Committees Contact


 
LINE

 
LINE
 
LINE
 
LINE
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
LINE
 
LINE
 
LINE
 
LINE

Notify me by Email
 

City of Ashland, Oregon / City Recorder / City Council Information / Packet Archives / Year 2002 / 01/15 / RESO - WWTP

RESO - WWTP


[Council Communication]   [ Proposed Resolution ]   [WWTP Cost Summary in PDF Format


Council Communication
Submitted By: Lee Tuneberg and Paula Brown
Reviewed By: Paul Nolte
Approved  By: Greg Scoles

Title:  Update on Remaining Wastewater Treatment Plant Construction Work and approval of increase in funding from Clean Water State Revolving Fund.

Synopsis: The City has been constructing major improvements to the Wastewater Treatment Plant facility under a contract with Slayden Construction (Slayden) since September 1998. Originally the wastewater treatment plant improvements were designed as two distinct pieces; the initial phase as process improvements at the wastewater treatment plant site (Project A), and the second phase (Project B) for facilities to be constructed on the City's hillside farmland for effluent reuse and biosolids application.

Council has directed the process improvements to include new membrane filtration facilities and centrifuge biosolids handling facilities that do not depend on land application of either effluent or biosolids. The Department of Environmental Quality has mandated completion for the new membrane filtration improvements so that all permit limits are met and achieved by May 1, 2002.

The project is partially funded through an Oregon Clean Water State Revolving Fund Loan. Payments on this loan will begin November 2002. The interest rate per the agreement is 3.43% which remains as an advantage to the city despite recent fluctuations in the markets. This communication is consistent with the past practice to annually come to Council for approval before amending the loan.

Recommendation: It is recommended that the Council approve the resolution for additional loan obligation, increasing the authorized amount to $23,420,068.
Fiscal Impact: A year ago, staff estimated the additional facilities to be between $10 - 10.5 Million (for a grand total of $26.6 Million plus design, redesign and construction management; $31.8 - for the total project). Current cost analysis includes all of the costs to date and are shown on the attached document. The thcilities costs remain at $26.5 Million. Design costs have increased to $5.2 Million and the prior land and wetlands demonstration project bring the grand total for the WWTP Upgrade project to $33.2 Million.
Background: Membrane Facilities: The membrane filtration pilot testing program was completed in December 2000. Council approved staff and Carollo's recommendation to sole-source the purchase of the Zenon Zeeweed membrane filtration unit as it operated well during the pilot testing and met all treatment objectives during the entire pilot period. The Zenon technology provides necessary operational flexibility. The submerged design of Zenon has the advantage of providing additional flocculation time in the membrane tank. The Zenon Zeeweed is a vacuum system in which air is used to agitate and clean the membranes. This air agitation injects dissolved oxygen into the final effluent as required in the City's NPDES discharge permit. The Zenon system requires no additional facilities for tertiary clarification.

Staff, Carollo and Slayden Construction collaborated on a fast track design and building project. The membrane facility is approximately 35% complete. All of the Zenon equipment is on site. It is anticipated that the system will be operational in April so that the City will meet the DEQ deadline of May 1, 2002. The costs of the facility, piping, pumping, ancillary equipment were negotiated a section at a time with Slayden Construction. Each change order had an independent review of costs and was further negotiated. All of the construction, including the prior yard piping changes incurred a total cost of $3,873,092. The Zenon Zeeweed unit itself was negotiated for a total of $2,512,500. The total membrane facility costs are $6,385,592 and are consistent with the original estimate of $6 million.

Dewatering and Biosolids Management: At the September 19, 2000 Council meeting, Council directed staff to pursue biosolids options that would not utilize land application, specifically not used the City's off-site EFU properties for any biosolids application. The biosolids management portion at the wastewater treatment plant is the final piece of a multi-year project. Several options have been explored and City staff members have visited several different treatment plants throughout the western United States to evaluate the best options for the City. After discussions with our consultant, Carollo Engineers, and discussions with treatment plant operators, staff is convinced that using a centrifuge system that allows both thickening and dewatering is the best option to pursue. Building the facility at the wastewater treatment plant ensures long-term quality control and the ability to modify operations for a higher class material should the City desire to use the biosolids for reuse. At the August 18, 2001 Council Study Session, Council discussed and accepted staff's direction to go forward with a centrifuge facility. The design for the biosolids facility has begun and will be completed by April. The facility itself will be negotiated and hopefully under construction in May 2002. Initial cost estimates for facility, piping, pumping, centrifuge mechanism and potential future air scrubbing to reduce odors remain within the $4.4-$4.6 M range.

CWSRF Funding: The City obtained a loan from the Oregon Department of Environmental Quality, Clean Water State Revolving Fund loan program. The original loan amount was $17,969,671. This amount was increased to $21,767,068 in December 2000, and subject to Council's approval of the attached resolution, will be revised again to a new loan amount of $23,920,068. The CWSRF program offers the City excellent rates for repayment. The additional loan encumbrance will be repaid through rates and the meals tax.

Remaining Issues: 1) A new permit for discharge to Ashland/Bear Creek will require development of a temperature management plan. The temperature limits have not yet been specifically determined for Bear Creek. This is still an issue to be negotiated and determined by DEQ. Staffand Carollo are developing the Temperature Management Plan documentation. 2) The future use or disposition of the City's EFU land is still pending. The current use of that land is through a contract with a farmer for cattle grazing.

End of Document - Back to Top



RESOLUTION NO. 2002-

A RESOLUTION AUTHORIZING AND APPROVING AN INCREASE IN THE
AMOUNT BORROWED FROM THE CLEAN WATER STATE REVOLVING
FUND FOR THE WASTEWATER TREATMENT FACILITIES PROJECT AND
REPEALING RESOLUTION 2001-03.

RECITALS:

A. The City of Ashland (the "City") has entered into negotiations with the State of Oregon Department of Environmental Quality (the "DEQ") for a loan to the City from the Clean Water State Revolving Fund in the amount of $23,420,068, which increases the previously adjusted loan value by $1,653,000.

B. The DEQ has provided to the City a form of the amended Clean Water State Revolving Fund Agreement. ("CWSRF")

C. The City Attorney and Finance Director are finalizing this agreement.

THE CITY COUNCIL OF THE CITY OF ASHLAND RESOLVES:

Section 1. City authorizes and approves the form of the CWSRF Loan Agreement for the increased amount to finance the Wastewater Treatment Facility Project.

Section 2. City authorizes and approves the establishment and funding of a designated reserve account to meet the "Loan Reserve" requirement of the CWSRF Loan Agreement, and directs the Director of Finance to establish this Loan Reserve.

Section 3. City authorizes and approves the establishment and funding of a Wastewater Rate Stabilization Account. The purpose of this account is to mitigate rate shock when the Food and Beverage Tax sunsets. City directs the Director of Finance to establish this account.

Section 4. City authorizes and directs the Director of Finance and the City Administrator, acting for and on behalf of the City, to execute the final CWSRF Loan Agreement and such other and additional documents as may reasonably be required for the consummation and closing of the Loan, and any amendments required thereafter.

Section 5. Resolution 2001-03 is repealed.

Section 6. This resolution takes effect upon signing by the mayor.

This resolution was read by title only in accordance with Ashland Municipal Code 2.04.090 duly PASSED

and ADOPTED this __ day of __________________________,2002.

SIGNED and APPROVED this __ day of ______________________,2002.

.

End of Document - Back to Top



WWTP Cost Summary for 2002:

This cost summary is available as a PDF file.  Click on the link below to download and view the document:






Download File
WWTP_Cost_Summary_2002.pdf

(54.1KB)
 

Get Acrobat Reader The above document(s) are Adobe® Acrobat® PDF files and may be viewed using the free Adobe® Acrobat® Reader™. Most newer web browsers already contain the Adobe® Acrobat® Reader™ plug-in. However, if you need it, click on the "Get Acrobat® Reader™" icon to download it now.

 

printer friendly version Printer friendly version

If you have questions regarding the site, please contact the webmaster.
Terms of Use | Built using Project A's Site-in-a-Box ©2012

View Mobile Site

News Calendar Agendas NewsCalendarAgendasFacebook Twitter