City of Ashland, Oregon / City Recorder / City Council Information / Packet Archives / Year 2001 / 12/18 / Siskiyou
Siskiyou
[Council Communication] [Siskiyou
Analysis]
Council Communication
| Title: |
Approval of Design Elements Regarding Siskiyou
Boulevard |
| Dept: |
Public Works Department |
| Date: |
December 18, 2001 |
| Submitted By: |
Paula Brown |
| Reviewed By: |
Greg Scoles |
| Synopsis: |
At the December 5th study session, staff provided
the Council with a preview of several design details and an update of the
design process. On December 6th, staff and the design team lead by W&H
Pacific, presented this same information to various business people affected
by some of the changes and also held a public Open House to hear comments
and concerns regarding the overall design. At the study session, Council
was alerted that a decision would be necessary on December 18th for several
specific elements of the Boulevard design. Particularly, staff would need
concept approval for both the Ashland Street (Hwy 66) to Walker section and
the intersection of Lithia Way, E. Main and Siskiyou.
The final design is on schedule. With Council's decision, the design
team will continue toward final design and bring the 85-90% design to the
community and Council for final acceptance in March 2002. Final design details
will then be completed so that the project can go to bid in May. Construction
is on schedule for mid-July 2002 and completion by December 2003. |
| Recommendation: |
Staff recommends the following actions by
Council:
1) Reject the initial concept of the roundabout
at the intersection of Siskiyou / Lithia Way / E. Main and return to a more
traditional signalized intersection. Direct staff to evaluate traffic circulation
and bring a recommendation to Council by February on the inclusion of 3rd
Street and Gresham as a part of the revisions to the intersection.
2) Accept the compromise solution (drawing to
be provided at the meeting) for the Ashland Street to Walker Avenue section
of the project.
3) Accept staff's recommendation to close the
end of Iowa at Siskiyou with a closure detail that will be acceptable to
the Fire Department and their access requirements.
4) Accept staff's recommendation to realign
Beach Street, modify the current traffic signal and negotiate with the property
owner for these improvements.
5) Accept W&H Pacific's recommendation to
NOT include the signal at Morton Street, as it does not meet current signal
warrants. The design could include the necessary undergrounding elements
so that a future signal could be easily accommodated once the signal warrants
are met.
|
| Fiscal Impact: |
These decisions to not impact the current funding
estimate. Staff remains confident that the project will be completed within
the original $2.2 million estimate. The consultant team is optimizing the
need for structural repairs and asphalt overlay, and will also look to retain
as much of the existing infrastructure, mostly sidewalks, yet still ensuring
that all of the necessary drainage improvements and ADA requirements are
met.
The City has requested an additional $500,000 in OTIA funds from ODOT.
To date, the Ashland "Roundabout" project is included on the recommendation
project list for additional ODOT funding and expects the additional $500,000
once the Oregon Transportation Commission approves the statewide package.
Staff has initialized discussions with ODOT and will modify the project
prospectus to include the provisions for a signalized intersection rather
than the initial project proposal for the roundabout. The need for improvements
to the intersection has not changed, just the proposed solution and
design. |
| Background: |
There are two sections of the project that have not
yet received concept approval; the Ashland Street to Walker section and the
intersection of Lithia Way, E. Main and Siskiyou. There are also details
of the project that continue to arise that staff would like Council support
and approval. All of the traffic analyses and evaluations that lead to these
recommendations are included in the attached memo from Transpo.
Lithia Way / E. Main / Siskiyou Intersection:
Initial roundabout discussions were proposed as a part
of the Downtown Plan for the intersections of Lithia Way, E. Main and Siskiyou.
Initial review of the roundabout option was presented to Council on September
5th as staff provided an update on all of the City's Transportation Projects.
The W&H Pacific design team has reviewed the current and projected traffic
volumes and presented this information to the Council on December 5th. The
proposed roundabout failed to function with future traffic volumes. The option
of a signalized intersection was evaluated and showed improvements to the
function of the intersection if there were additional modification to the
traffic on 3rd Street. Additional evaluation is needed to see how these changes
impact overall traffic circulation and Gresham Street. This evaluation and
a recommendation will be brought back to the Council in February.
Ashland Street to Walker: The Ashland Street
to Walker section of Siskiyou Boulevard has also received additional review.
Reviews of traffic volumes show similar impacts for the use of either a 3
lane or a 5 lane option. The current volumes demonstrate that a 3 lane section
would operate well. However, as the consultants have looked at future volumes,
there is some concern that a 3 lane section might have cars backing up at
the signal that could block entrances to some of the business accesses in
the commercial "triangle". With that in mind, and with further discussions
with the affected business owners, a compromise solution was recommended.
This compromise (drawing to be provided at the meeting) includes:
· bike paths on both sides - preferably 6 feet in width;
-
a single lane in the southbound direction;
-
a single lane in the northbound direction from Walker to Francis Lane
- then continuing with two lanes northbound from Francis to the
intersection with Ashland Street;
-
a middle left turn lane (no median) throughout the section (except
right at the intersection across from Omar's as described below);
-
enhanced landscaping and some parking/loading bays on the west side
of the road along the entire stretch past Omar's, and on the east side of
the road in sections between Francis and Walker;
-
a short section of raised median at the intersection of Siskiyou and
Ashland Street in front of Omar's Restaurant which will act as both a pedestrian
refuge and as a barrier restricting cars coming out of the northern entrance
of the Omar's parking lot to a right in - right out movement (not allowing
left turns at the initial driveway which is in the intersection). This detail
will need to be developed further and discussed with both Omar's and SOU.
Although this recommendation is a compromise, it will allow the business
properties in the "triangle" to retain all of their access points and will
also provide an additional lane so that the travel movements into and out
of that area have additional space. That second northbound lane will also
allow for additional queuing length at the signal in future years. While
this solution does not fully meet the desires of some business owners who
would rather have no changes at all, others see a benefit to additional parking,
loading zones, landscaping and pedestrian safety elements.
Closure of Iowa Street: Staff is recommending
closure of Iowa Street at Siskiyou with a closure detail that will be acceptable
to the Fire Department and their access requirements. This was recommended
during the Otak Concept design and is being moved forward with the final
design. There have been several safety items brought to the Traffic Safety
Commission for consideration including this closure.
Realignment of Beach Street: The realignment
of Beach Street was being brought up to resolve the skewed intersection and
to improve the signal operations and traffic flow. Staff has not contacted
the affected property owner but is prepared to do that with Council's approval
of this recommendation.
Morton Street Signal: The signal at Morton Street
was shown on the initial Otak Report, but was reviewed by Transpo (W&H
Pacific's traffic engineering group), as it does not meet current signal
warrants. Having the two signals within two blocks of each other can cause
traffic flow problems and the consultant recommended that this be delayed
pending the future need. Although the signal is not necessary today, the
design could include the necessary electrical conduits and other undergrounding
elements so that a future signal could be easily accommodated once the signal
warrants are met.
Open House: Staff estimates that we had over
100 people at the open house and received 20 comment sheets. Most of the
verbal comments were positive. The majority of the written comments dealt
with the need to fully evaluate the 3rd Street/Gresham Street decision and
there were a few concerns with the closure of Iowa. Staff will have a summary
available for Council at the meeting.
The Boulevard Citizen Design Committee, BCDC, appointed by the mayor
and council continues to serve the community well. They spend a considerable
amount of time developing and shaping recommendations for the final design
criteria that is used by the consulting team. Their level of input will increase
as the details of the final design are now taking shape. |
End of Document - Back to Top
Siskiyou Boulevard Traffic Operations Analysis
Introduction
The purpose of this memorandum is to summarize the results of the traffic
operations review of future projects on Siskiyou Boulevard in the City of
Ashland Oregon. The study area is divided into three sections: 1) Gresham
Street/3rd Street/Lithia Way/East Main Intersection, 2) Siskiyou Boulevard
from 4'h Street to Ashland Street (Highway 66), and 3) Siskiyou Boulevard
from Wightman/Indiana Street to Walker Street. This memorandum will document
the expected traffic operations resulting from changes on the street system
in each of the three studysections for the present year as well as the forecast
year of 2020.
Background
Siskiyou Boulevard (also known as Oregon Highway 99) is a five-lane roadway
with a center turn lane and/or landscaped median, and with sidewalks along
the entire project length. The project limits, between 4th (Gresham) Street
and Walker Avenue, is 1.2 miles in length. There are five signalized
intersections within the project limits. All other intersections are
unsignalized. Siskiyou Boulevard is a major pedestrian thoroughfare that
connects Southern Oregon University (SOU), Ashland High School, and Lincoln
School to the Downtown area. Limited parallel parking is available on Siskiyou
Boulevard, primarily on the south side in the general area of the northwestern
project terminus.
The City of Ashland has received funding from the Oregon Department of
Transportation (ODOT) for a modernization project for the 1.2-mile section
of Siskiyou Boulevard. The project has a tentative construction start date
of June 2002. As part of the improvement project, the City is assuming ownership
of the project section from ODOT.
The City appointed the Siskiyou Boulevard Citizen Design Committee (BCDC)
to serve as the community liaison group for public involvement and was charged
with facilitating public discussion and reaching consensus on project design
elements. Through a community-based visioning process sponsored by BCDC and
a series of focused community workshops, an Opportunities and Constraints
Analysis identified significant design considerations to guide the development
and evaluation of alternative concepts. A series of design concepts were
prepared and evaluated and a design section for the 4th to Walker portion
of Siskiyou Boulevard was recommended to City Council. The preferred design
section is documented in theSiskiyou Boulevard Design Concepts report prepared
by OTAK and dated February 2001.
The preferred design concept provides recommendations for landscape and
streetscape treatments in both districts including pedestrian-scale lighting
for intersection crosswalks, crosswalk treatments, special street signs and
streetscapes compatible with the unique character of the historic and
"storefront" atmosphere of the districts. It also identifies several items
in need of further analysis including.-
1. Evaluate the operations and recommend traffic flow changes to the Gresham
Street, Siskiyou, Lithia Way and Main Street intersection at the fire station
and library
2. Evaluate limiting University Way to a fight-out only by extending the
median along Siskiyou Boulevard
3. Evaluate reducing the number of lanes from 5 to 3 on the section of Siskiyou
from Ashland Street to Walker Avenue
4. Evaluate implementing a wide promenade concept in the University District
through a joint effort between the City and SOU since the existing right-of-
way will not accommodate the proposed width of the walkway.
This document will examine expected traffic operations of the above design
concepts 1-3.
Traffic Operations Evaluation Approach
The data will primarily be quantified with the use of two transportation
evaluation tools; Synchro and Vissim. Synchro is an operations model that
evaluates and calculates the levd of service for coordinated systems of traffic
signals. Synchro is based on methodologies consistent with the Highway ~
Manual, 2000 Edition. Synchro will be used to estimate intersection levels
of service. Vissim is a microscopic traffic simulation model used to model
urban traffic and public transit operations. Vissim has the capability to
analyze traffic, transit and light rail operations under many different geometric
and operational constraints, such as different lane configurations, traffic
compositions, traffic signals, transit routes and stops. Vissim will provide
a complete animated representation of existing and future operations of the
transportation system, based on technical data. Vissim will also provide
technical output for comparative analysis.
Gresham Street/Siskiyou/Lithia Way/East Main Intersection
This intersection was analyzed under three scenarios during the PM peak hour.
The three scenarios included: 1) roundabout with existing traffic volumes,
2) roundabout with future 2020 traffic volumes, and 3) signaliTed with future
2020 traffic volumes. The roundabout option was evaluated using Vissim and
the signaliTed analysis was done using Synchro. This section documents the
data coded into the models as well as the results.
Existing Traffic Volumes
Typically for traffic operations analysis the peak hour traffic volume is
used to provide a conservative estimate of the traffic operations during
the heaviest use of a facility. The peak hour is a single hour during a typical
day in which the maximum traffic volume occurs on a given facility. The peak
period varies from facility to facility but is common during a PM hour that
captures commuter traffic.
PM peak hour traffic volumes were used for this project to estimate the traffic
operations of a roundabout and signal at this intersection. PM peak hour
traffic volumes were derived from Average Daily Traffic (ADT) data provided
by the City of Ashland staff. It was assumed that the PM peak hour traffic
volumes represented 10 percent of the ADT.
Future 2020 Traffic Volumes
The Intersection was also evaluated under forecast 2020 traffic volume
conditions. City staff provided existing traffic volumes and forecast 2019
traffic volumes at several locations along Siskiyou Boulevard. This data
was used to develop an annual average growth rate, which was applied to existing
traffic volumes. Based on the data provided an average annual growth rate
was estimated at approximately 1 percent. To provide a conservative traffic
operation analysis a 1.5 percent annual growth rate was used. The 2020 estimated
volumes are also shown in Figure 1.
Roundabout Analysis
Vissim was used to estimate the traffic operations at this intersection with
a roundabout used for traffic control. The analysis was performed with both
existing and 2020 traffic volumes. It was assumed that all turning movements
that currently use the intersection would continue to use the intersection,
and that pedestrians would continue to cross the street system at similar
locations and frequency as they do today. Furthermore, it was assumed that
vehicles approaching the roundabout would yield to vehicles in the roundabout.
The results of the analysis are shown inTable 1.
Table 1
Roundabout Operations - Existing Volumes verses 2020
Volumes |
| . |
Existing Volumes
Queue (feet) |
2020 Volumes
Queue (feet) |
| Approach |
Delay (sec) |
xx Ave - (xx) Max |
Delay (sec) |
xx Ave - (xx) Max |
| East Main (one-way) |
13 |
10 - (400) |
23 |
35 - (795) |
| Siskiyou Blvd NB |
48 |
175 - (730) |
261 |
1945 - (2295) |
| East Main (two-way) |
12 |
25 - (265) |
17 |
40 - (345) |
As Table 1 shows, the Sisldyou Boulevard northbound approach is impacted
the most by the expected operations of a roundabout at this location. Us'rog
existing traffic volumes, the Siskiyou Boulevard is expected to have 48 seconds
of delay with a queue that will vary between 175 and 730 feet depending on
demand. This means that it takes a vehicle approximately 48 seconds to get
from the end of the queue to entering the roundabout. The delay on Siskiyou
is expected to increase to 261 seconds (4 minutes 21 seconds). This length
of delay will be unacceptable with 2020 conditions.
One option was reviewed that might help the roundabout work better. Much
of the delay on Siskiyou Boulevard is due to the high volume of conflicting
movements coming from East Main Street (one-way) going to Lithia Way and
eastbound on East Main Street (two-way). The Siskiyou Boulevard vehicles
must yield to the East Main movements that are going to Lithia Way and eastbound
on East Main Street. The idea is to divert the conflict'mg traffic volume
that is going to Lithia Way, which are approximately 220 vehicles during?20
conditions. These vehicles would be diverted to Lithia Way via 34 Street.
3 d Street would need to be changed to two-way operation. The vehicle diversions
are shown in Figure 2. The results of the traffic volume shift are shown
in Table 2.
Table 2
Roundabout Operations - 2020 Volumes verses Lithia Way
Volumes |
| . |
2020 Volumes
Queue (feet) |
2020 Volumes (Lithia Way diversions)
Queue (feet) |
| Approach |
Delay (sec) |
xx Ave - (xx) Max |
Delay (sec) |
xx Ave - (xx) Max |
| East Main (one-way) |
23 |
35 - (795) |
19 |
15 - (550) |
| Siskiyou Blvd NB |
261 |
1945 - (2295) |
158 |
158 - (2290) |
| East Main (two-way) |
17 |
40 - (345) |
40 |
140 - (495) |
Diverting the traffic volume between East Main and Lithia Way to 3rd Street
improves the delay on Sislo/ou Boulevard from 261 seconds (4 minutes 21seconds)
to 158 seconds (2 minutes 38 seconds). Although Siskiyou Boulevard'sdelay
improved with the vehide diversion, East Main Street (two-way) delay increased
from 17 seconds to 40 seconds. This is due to the greater volumes of traffic
entering the roundabout northbound from Siskiyou providing fewer gaps for
the East Main (two-way) vehides. With the traffic diversion to 3~d Street
there were less conflicts in the roundabout and the northbound Siskiyou vehicles
were more able to enter the roundabout, thus reducing the number of useable
gaps for vehicles entering from East Main (two-way) approach.
Based on the roundabout operations analysis, a roundabout does not function
well at this intersection. This is primarily due to the high north-south
traffic follows, high frequency of vehicle turning movement conflicts within
the roundabout, and high pedestrian activity.
Signalized Analysis
Synchro was used to analyze the intersection under signalized operation.
The intersection was analyzed with future 2020 traffic volumes only. All
existing turning movements were accommodated by the intersection. The turning
movements and phasing are shown in Figure 3. Similar to the roundabout, a
second alternative was analyzed where the volume from East Main to Lithia
Way was diverted to Lithia Way via 3~a Street. This diversion allowed a signal
phase to be dropped from the signal-timing plan, thus providing more green
time for the heavy traffic volumes on the major streets. The signalized traffic
operations are based on level of service analysis.
Signalized intersection level of service is based on the average total vehicle
delay of all movements through an intersection. Vehicle delayis a method
of quantifying several intangible factors, including driver discomfort,
frustration, and lost travel time. Specifically, level of service criteria
is stated in terms of average delay per vehicle during a specified time period
(for example, the PM peak hour). Vehicle delay is a complex measure based
on many variables, including signal phasing (i.e., progression of movements
through the intersection), signal cycle length, and traffic volumes with
respect to intersection capacity. The detailed level of service criteria
is described in the Highway Capacity Manual Transportation Research
Board, Special Report 209, 2000). The results of the analysis are shown in
Table 3.
Table 3
East Main, Siskiyou, Lithia Way Signalized Analysis
| Weekday PM Peak Hour |
Future 2020 Conditions |
2020 Volumes (Lithia Way Diversions) |
| |
LOS |
Delay |
V/C |
LOS |
Delay |
V/C |
| Signalized Intersection |
F |
>80.0 |
>1.20 |
C |
24.5 |
0.97 |
As Table 3 shows, the intersection is expected to operate at LOS F during
2020 conditions without the traffic diversions. The intersection is expected
to operate at LOS C during 2020 conditions with the East Main to Lithia Way
traffic volumes diverted to 3rd Street.
Summary
It is recommended that a roundabout not be used as a traffic control tool
at the intersection of East Main/Siskiyou Boulevard/Lithia Way. It is also
recommended that the southbound to northbound U-Turn movement from East Main
to Lithia be accommodated by converting 3rd into a two-way street. This will
ensure that the future traffic signal will operate at an acceptable level
of service and more importantly will simplify the intersection configuration
at the couplet.
Siskiyou Median Extensions and Traffic Diversions
Traffic circulation along Siskiyou Boulevard was evaluated with the access
limitations (projected median through the intersections at Union, Harrison,
Liberty and Palm/University Way) with two new signals at Sherman and Morton.
Also, the conversion of University Way to a right in only and the redirection
of traffic as a result of this access limitation was evaluated.
This section of the memorandtun reviews three scenarios: 1) Left-turns being
diverted due to median extensions, 2) University Way traffic flow revision,
and 3) Iowa Street closure. The analysis was performed using the Synchro
traffic operations analysis software. The baseline analysis year for this
project is 2003.
Existing Traffic Volumes
Existing PM peak hour traffic volumes were based on the existing (year 2000)
traffic volumes presented in the "Siskiyou Boulevard Design Concepts" report
prepared by Otak, February 2001. The volumes were forecast to year 2003 by
assuming an annual growth rate of 1.5 percent for 3 years in this section
of Siskiyou. The traffic volumes used to establish baseline are presented
in Figure 4.
Signal Timing
Existing signal timings were provided by the Oregon Department of Transportation
(ODOT) for the signalized intersections along Siskiyou Boulevard. All signal
timing is based on the timing plans sent by ODOT.
Future 2020 Traffic Volumes
Future 2020 traffic volumes were developed to ensure the traffic system would
continue to operate well under future conditions. City staff provided existing
traffic volumes and forecast 2019 traffic volumes at several locations along
Siskiyou Boulevard. This data was used to develop an annual average growth
rate, which was applied to existing traffic volumes. Based on the data provided
an average annual growth rate was estimated at approximately 1 percem. To
provide a conservative traffic operation analysis a 1.5 percent annual growth
rate was used to develop future traffic volumes.
Left-Turn Diversions
The left-tum diversion analysis assumes that the Siskiyou Boulevard median
will be extended through the intersections of Union, Harrison, Liberty and
University. The traffic will be diverted to the signalized intersections
of Sherman, Morton, Beach, and Mountain. The volume diversions can be seen
graphically in Figure 5.
The left-turning traffic at Union is expected to move to Sherman. The net
traffic volume at Sherman is expected to increase by 20 mph. The northbound
left-turn increases by 20 mph and 20 vehides that used to go through Sherman
to access Union will now turn left at Sherman.
It was assumed that the left-tums from Harrison and Liberty would divert
to Morton. Morton would experience approximately 95 new trips per hour. The
north-to-west left-turn on Morton would increase from 15 mph to 50 mph and
the west-to-south left-turns would increase from 30 mph to 120 mph. The westbound
through trips would decrease by 30 mph. No new trips were assigned to
Beach/Morse.
The left turn trips from University Way were assigned to Mountain. At Mountain,
the north-to-west left-turn is expected to increase from 140 to 165 mph,
and the northbound through trips are expected to increase from 40 to 45 mph.
The south-to-eastbound trips are expected to increase from 85 to 90 mph.
The east-to-north left-turns are expected to increase from 60 to 80 mph and
the eastbound through trips are expected to decrease by 20 trips. The westbound
through trips are expected to decrease by 25 mph. This is a net increase
of 10 mph to the intersection. Most vehides that once traveled through the
intersection are now turning at the intersection of Mountain.
Left-turn Diversions Operations Analysis
The left-turn diversion impacts to the signalized intersections were analyzed
using the Synchro software. The impacts to the four signalized intersections
with increased traffic volumes are shown in Table 4, as well as the expected
condition in the year 2020.
Table 4
Left Turn Diversion Operations
Weekday PM Peak Hour
Siskiyou Blvd at: |
2003 Baseline |
2003 with Diversions |
| . |
LOS |
Delay |
V/C |
LOS |
Delay |
V/C |
| Sherman |
A |
8.6 |
0.52 |
A |
9.2 |
0.51 |
| Morton |
A |
7.9 |
0.51 |
A |
8.6 |
0.54 |
| Morse/Beach |
B |
12.5 |
0.53 |
B |
12.5 |
0.53 |
| Mountain B |
B |
14.8 |
0.52 |
B |
16.5 |
0.58 |
| Siskiyou Blvd at: |
2003 with Diversions |
2020 with Diversions |
| Sherman |
A |
9.2 |
0.51 |
B |
10.1 |
0.63 |
| Morton |
A |
8.6 |
0.54 |
A |
9.9 |
0.58 |
| Morse/Beach |
B |
12.5 |
0.53 |
B |
16.6 |
0.68 |
| Mountain B |
B |
16.5 |
0.58 |
C |
23.3 |
0.79 |
As Table 4 shows, the shifts in traffic volume due to the median extensions
is not expected to degrade the level of service at the signalized intersections.
The results of this analysis are reasonable since the vehicle volumes being
shifted are relatively small. The analysis also indicates that the signalized
intersections are expected to operate well under 2020 conditions.
University Way Right In Only
Under this scenario it was assumed that the traffic flow on University would
be reversed from one-way outbound flow to one-way inbound flow onto Siskiyou
Boulevard. The outbound traffic on University was shifted to Mountain, and
half of the existing southbound right-tums at Mountain were shifted to
University. This scenario also assumes the median extension at University
exist such that those lefts are diverted to Mountain, as was the case in
the previous scenario.
As shown in Figure 5, the outbound traffic volumes were already shifted to
Mountain due to the median extensions. Thus, the only outbound volume shifted
to reverse flow on University Way was the 60 right out vehides.
University Way Right In Only Operations Analysis
Shifting the flow of traffic on University will primarily impact Mountain
Avenue because most of the traffic will divert to Mountain. University Way
is expected to operate well because with the median extension traffic flow
will be right in only at University. The expected impacts of shifting more
traffic from University to Mountain were evaluated with Synchro. The results
of the analysis are shown in Table 5.
Table 5
University Traffic Flow Reversed
Weekday PM Peak Hour
Siskiyou Blvd at: |
2003 with Diversions |
With NB Traffic From University |
|
LOS |
Delay |
V/C |
LOS |
Delay |
V/C |
| Mountain |
B |
16.5 |
0.58 |
B |
16.6 |
0.58 |
| Weekday PM Peak Hour |
With NB Traffic From University |
2020 With Traffic From University |
| Mountain B |
B |
16.6 |
0.58 |
C |
23.4 |
0.79 |
As Table 5 shows, shifting the additional traffic to Mountain from University
to accommodate the change in traffic flow is not expected to degrade the
level of service at Mountain. Based on the 2020 analysis, Mountain is expected
to continue to operate at an acceptable level of service.
Iowa Closed
This scenario assumes that Iowa Street is dosed at the location where it
intersects Siskiyou Boulevard and Beach/Morse Street. The traffic approaching
Siskiyou/Beach/Morse was rerouted to Morton Street. Thus, at Morton Street
the northbound left-turn was increased by 20 mph; the through trips were
increased by 20 mph; and the right-tums were increased by 70 mph. The analysis
also assumes the same traffic diversions that were used for the median extension,
assuming Iowa would be closed as well as the median extension project.
Iowa Closed Operations Analysis
Closing Iowa Street will impact Siskiyou Boulevard at the intersections of
Morton and Beach/Morse. The expected impacts of shifting more traffic from
Iowa to Morton and closing Iowa at Beach/Morse were evaluated with Synchro.
The results of the analysis are shown in Table 6.
Table 6
Iowa Closed
Weekday PM Peak Hour
Siskiyou Blvd at: |
2003 with Diversions |
With Iowa Closed |
|
LOS |
Delay |
V/C |
LOS |
Delay |
V/C |
| Morton |
A |
7.9 |
0.51 |
A |
9.9 |
0.61 |
| Morse/Beach |
B |
12.5 |
0.53 |
A |
5.3 |
0.41 |
| Weekday PM Peak Hour |
With Iowa Closed |
2020 With Iowa Closed |
| Morton |
A |
9.9 |
0.61 |
B |
13.3 |
0.68 |
| Morse/Beach |
B |
5.3 |
0.41 |
A |
6.4 |
0.53 |
Table 6 shows, both intersections will continue to operate well if Iowa Street
is closed. Morton is expected to continue to operate at LOS A. And Morse/Beach
is expected to increase from LOS B to LOS A. Morse/Beach improves because
one less signal phase is required at this intersection when Iowa is closed.
Thus, more green time is available to process vehicles at the remaining
approaches. As Table 6 shows, both of these intersections are expected to
operate well with forecast 2020 traffic volumes
Summary
As the traffic operations analysis in this section shows, extending medians,
closing streets, and reversing traffic flow on University is not expected
to degrade the level of service at the signalized intersections on Sisldyou
Boulevard between Union and University. This is primarily due to the low
traffic volumes on the side streets that are impacted by the infrastructure
adjustments. Shifting these low volumes to the signalized intersections is
not expected to significantly increase delays or queues at the signalized
intersections analyzed. Furthermore, with the proposed changes, the intersections
are expected to continue to operate well in the forecast year of 2020.
Siskiyou Boulevard - Hwy 66 to Walker (5 vs. 3-Lanes)
This section of the memorandum documents the analysis of Siskiyou Boulevard
from Indiana/Wightman to Walker Avenue. The traffic operations analysis consisted
of evaluating existing and future (2020) traffic volumes and circulation
of two street system altematives. The alternatives analyzed include the existing
system with 5-Lanes (Existing 5-Lane) and an alternative concept with 3-Lanes
(Future 3-Lane Option) between Highway 66 and Walker Avenue. The traffic
analysis was performed using micro-simulation (Vissim).
As discussed earlier, Vissim is capable of accounting for the interaction
of every vehicle within a network Thus, Vissim will provide detailed information
of vehicle impacts to up/downstream intersections and driveways.
Baseline (2003) Traffic Volume Test
This section of the report documents the results of the 5-Lane and the 3-Lane
option traffic operations using baseline (2003) volumes. The same traffic
volumes were used for each option. However, the signal timing data was adjusted
for the 3-Lane option to account for the geometric reductions in capacity
as well as for some turning movement adjustments at Siskiyou Boulevard/Highway
66. In addition the 5-Lane option included a single south to east left turn
lane as exists today, while the 3-Lane option was evaluated with two south
to east left lanes. The two left turn lanes were added to accommodate the
heavy vehicular demand for this movement and to improve the overall operation
of the intersection.
Traffic Volumes
Existing traffic volumes were based on the turning movement counts provided
in the Siskiyou Boulevard Design Concepts" report prepared by Otak, February
2001. The volumes were forecast to year 2003 by assuming an annual growth
rate of 1.5 percent for 3 years. The PM peak volumes are shown in Figure
6.
Signal Timing
Existing signal timing information was provide by the Oregon Department of
Transportation (ODOT) for the Siskiyou Boulevard. All existing signal timing,
for the 5-Lane, is based on the timing plans sent by ODOT. Signal timing
was appropriately adjusted for the modifications made to the 3-Lane Option.
For the 3-Lane option the signal-timing plan at Siskiyou Boulevard/Highway
66 and Siskiyou Boulevard/Walker Avenue had to be adjusted to account for
the reduction in roadway capacity (i.e., the reduction in travel lanes).
Also, at Siskiyou Boulevard/Highway 66 a left-turn from Highway 66 to southbound
Siskiyou was included to provide maximum traffic circulation capability and
to avoid cut through traffic through private properties. Signal timing is
provided in the appendix.
Simulation Results
The existing traffic volumes, signal timing, and appropriate intersection
geometry were coded into Vissim. Data was collected for both the 5-Lane option
and the 3-Lane option. Queue data was collected at all approaches at Siskiyou
Boulevard/Highway 66 and travel times were collected on a segment of Siskiyou
Boulevard and Highway 66. The three travel times collected are:
1) Siskiyou southbound, beginning north of Wightman St./Indiana St. and
ending south of Walker Ave.
2) Siskiyou northbound, beginning south of Walker Ave and ending north of
Wightman St./Indiana St.
3) Highway 66 westbound, beginning east of Siskiyou Boulevard and ending
north of W~ghtxnan St./Indiana St.
The purpose of the data collection is to measure the degree of change between
the different lane configuration options and volumes. Table 7 provides the
results of the queuing data collected at Siskiyou Boulevard/Highway 66.
Southbound queue measurement includes vehicles traveling through the intersection
on Siskiyou and turning left on to Highway 66. Northbound travel times include
vehicles traveling north through the Siskiyou/Highway 66 intersection; and
westbound includes vehicles traveling from Highway 66 turning onto Siskiyou.
Table 7
Siskiyou/Hwy 66 Queue Comparisons (2003)
| . |
5 Lane |
3 Lane |
| Approach |
Ave.(ft.) |
Max (ft.) |
Ave.(ft.) |
Max (ft.) |
| Southbound |
190 |
725 |
85 |
490 |
| Northbound |
15 |
145 |
55 |
335 |
| Westbound |
40 |
205 |
35 |
200 |
As Table 7 shows, the southbound queues are reduced due to the added left-tum
capacity provided by the dual-left from Siskiyou to Highway 66. The northbound
left is expected to increase due to the reduction in lane capacity, and the
westbound approach is expected to operate similar under both the 5-lane and
3-lane option The northbound queues could be mitigated by adding a second
though lane in the northbound direction. Table 8 provides the results of
the travel time analysis.
Table 8
Siskiyou Travel Time Comparison (2003)
Average Travel Time (seconds) |
| Route |
5 Lane |
3 lane |
| Southbound on Siskiyou |
75 |
85 |
| Northbound on Siskiyou |
75 |
85 |
| WB to NB Hwy 66 |
50 |
45 |
As Table 8 shows, the time to travel on Siskiyou between Wightman/Indiana
and Walker is expected to increase by approximately 10 seconds in each direction.
The increase of 10 seconds will probably not be discemable by most drivers
due to the fact that it is spread out over three intersections. Travel time
from Highway 66-to-Siskiyou should remain relatively consistent. Based on
2003 traffic volumes the 5-Lane and 3-Lane concepts are expected to operate
similar. The 3-Lane option improves the south-to-east left turn at
Siskiyou/Highway 66, and slightly degrades the westbound operations. This
is mainly due to converting one of thesouthbound through lanes in the 5-Lane
option to a left turn lane in the 3-Lane option.
Future 2020 Traffic Volume Test
This section of the report documents the results of traffic impacts to the
street system when traffic volumes increase over the next 17-years, from
2003 to 2020. Traffic volumes were increased at an annual growth rate of
1.5 percent for 17 years and the signal timing was recoded for both the 5-Lane
and 3-Lane options to account for the increase in traffic demand.
Future 2020 simulation results
The following two tables document the expected impacts to the 5-Lane and
3-Lane options due to increased traffic volumes over a 17-year period. Table
9 shows the impacts to traffic queues at Siskiyou/Highway 66 for 2020 compared
to the 2003 conditions.
Table 9
Siskiyou/Hwy 66 Existing vs. 2020 Expected Queues
| . |
Existing Volumes (2003) |
Future Volumes (2020) |
| . |
5 Lane |
3 Lane |
5 Lane |
3 Lane |
| Approach |
Ave. |
Max |
Ave. |
Max |
Ave. |
Max |
Ave. |
Max |
| Southbound |
190 |
725 |
85 |
490 |
110 |
625 |
200 |
890 |
| Northbound |
15 |
145 |
55 |
335 |
35 |
250 |
70 |
440 |
| Westbound |
40 |
205 |
35 |
200 |
35 |
235 |
50 |
280 |
The approximate distance between the Highway 66 intersection and Wightman/Indiana
is 220 feet. As Table 9 shows, the average queue should be less than 220
feet under all scenarios for the southbound direction. The maximum queue
is expected to extend through the Wightman/Indiana intersection a few times
every PM peak period. The average eastbound queues are not significant
considering the average is 200 feet, which is approximately equivalent to
10 vehicles (assuming average of 20 feet per vehicle). However, due to the
close proximity of W',ghtman/Indiana the queue becomes more significant due
to it impacts of pedestrian and vehide traffic at Wightman/Indiana. The
northbound and westbound queues are both expected to increase slightly in
2020. The impacts of increased traffic volume on travel time are shown in
Table 10.
Table 10
Siskiyou Travel Time ( seconds) Comparison
. |
Existing |
Future |
Route |
5 Lane |
3 Lane |
5 Lane |
3 Lane |
SB on Siskiyou |
75 |
85 |
70 |
80 |
NB on Siskiyou Wb to NB |
75 |
85 |
75 |
85 |
Hwy 66 |
50 |
45 |
50 |
50 |
As Table 10 shows, future 2020 traffic volumes are not expected to significantly
impact travel times through the study area. This is primarily due to the
adjustments made to the signal timing and the added south to east second
left turn.
The conversion of Siskiyou Boulevard from a 5-Lane to 3-Lane section between
Highway 66 and Walker does not negatively impact traffic operations along
this roadway segment. The analysis showed that minor congestion occurs on
Siskiyou Boulevard between Indiana and Highway 66. The 3-Lane option provides
enough capacity bebveen Highway 66 and Walker.
It is important to note that the current 5-Lane section between Highway 66
and Walker does not accommodate business deliveries in a safe and effident
manner since delivery trucks park in the two-way-left-mm-lane and cross two
lanes of traffic. The 3-Lane option provides an opportunity to add outside
parking lane and bicycle lanes on both sides of the street. The following
recommendations are proposed:
1. Convert the existing 5-Lane section into a 3-Lane section between
Highway 66 and Walker. The 3-Lane section should be configured with parking
and bicycle lanes on both sides of the Siskiyou and a potential second northbound
pocket at Highway 66.
2. At the intersection of Highway 66 and Siskiyou Boulevard, add a
second south to east left turn pocket by converting one of the existing
southbound through lanes.
3. Add a west to south left turn lane by converting the existing
two-way-left-
4. Modify the traffic signal at Highway 66 and Siskiyou to accommodate
the above recommendations.
5. Optimize the traffic signal timing plans at Highway 66 and
Indiana intersections
End of Document - Back to Top
|