City of Ashland, Oregon / City Recorder / City Council Information / Packet Archives / Year 2001 / 12/18 / Hwy 66 Project
Hwy 66 Project
[Council Communication] [Cooperative
Improvement Agreement]
Council Communication
| Title: |
Approval in Concept of Highway 66/Ashland Street
Project |
| Dept: |
Public Works Department |
| Date: |
December 18, 2001 |
| Submitted By: |
Paula Brown |
| Reviewed By: |
Paul Nolte |
| Approved By: |
Greg Scoles |
| Synopsis: |
On August 8, 2001, staff updated Council on options
for Highway 66 / Ashland Street from Siskiyou Boulevard south to Faith Avenue.
Currently, Highway 66 is under the Oregon Department of Transportation's
(ODOT) jurisdiction as a district level highway. This section of the highway
between Siskiyou Boulevard and Faith Avenue has been included as an ODOT
access management grant project. ODOT has drafted an agreement between ODOT
and the City to proceed with funding this project (attached). The current
design concept for the project includes raised median islands at two or three
locations, adjusting and if appropriate combining a few driveway accesses
to improve the adjacent sidewalks, and provide better pedestrian crossings
at several locations including potential traffic calming measures. The project
elements include design and construction of access management improvements
which include, but are not limited to; concrete driveways, sidewalks, raised
median, striping, paving, signage, landscaping and irrigation. In total,
ODOT is offering the City $450,000 for a completed project in which funds
must be expended by April 30, 2003. |
| Recommendation: |
Staff recommends that Council:
1.) Accept the attached ODOT agreement and authorize the Mayor
and City Recorder to sign the agreement.
2.) Direct staff to move forward with an expedited design and
construction schedule.
3.) Accept staff's recommendation to utilize the current Siskiyou
Boulevard Citizen Design Committee (BCDC) members and added community business
members to include Bill Cobb (State Farm); Tim Simonson; Randy Watt (Good
Times); Steve Meister; and Dennis Sweet as the Ad Hoc group.
4.) Direct staff to negotiate a change order with W&H Pacific
so that the design of the Ashland Street project is completed as a change
to W&H Pacific's current Siskiyou Boulevard Project.
5.) Direct staff to incorporate the construction of this project
as a part of the overall Siskiyou improvements so that it is completed by
April 30, 2003.
|
| Fiscal Impact: |
The City is agreeing to obtain grant funds from ODOT
in the amount of $450,000. The project must be completed and billed to ODOT
prior to April 30, 2003. Any work completed on this project after the April
30, 2003 deadline would be project costs borne by the City. Although there
are implications of potential jurisdictional exchange, these are to be agreed
through a separate and fully negotiated agreement with ODOT in the
future. |
| Background: |
There have been several different studies and evaluations
completed for Highway 66 / Ashland Street for the section from Siskiyou Boulevard
south to the City limits which is under the Oregon Department of Transportation's
(ODOT) jurisdiction as a district level highway. Staff requested ODOT's
assistance in determining the eligibility for an access management grant
for the section of Ashland Street between Siskiyou Boulevard to the beginning
of the railroad bridge (just past Faith Avenue) as there have been pedestrian
accidents and higher traffic speeds on this section. ODOT helped the City
develop a project outline and submitted the project for grant funding. The
grant has been approved and ODOT is willing to proceed with funding a project
to provide median islands in a few locations, adjust if appropriate a few
current accesses onto Highway 66, and provide better pedestrian crossings
at three locations for a cost of $450,000. Specifically called out in the
agreement proposed by ODOT, the project perimeters include:
"
the purpose of providing acceptable traffic patterns on
public highways, ODOT and City plan and propose to design and construct
access management improvements which include, but are not limited to; concrete
driveways, sidewalks, raised median, striping, paving, signage, landscaping
and irrigation,
"
The detailed parameters of the project's design are not yet established
and need to begin immediately. The concept is to improve this section of
Ashland Street so that it be improved for Ashland's benefit to include median
islands in appropriate locations and have better pedestrian crossings to
improve safety conditions. Staff is proposing to develop a final concept
plan with the help of an Ad Hoc citizen group that would include the current
Siskiyou Boulevard Citizen Design Committee (BCDC) and additional business
owners including: Bill Cobb (State Farm); Tim Simonson; Randy Watt (Good
Times); Steve Meister; and Dennis Sweet. Although these individuals would
be involved with the details of the design concept, staff will ensure inclusion
of the whole community through an open process. The design will be fast-tracked,
with kick-off meetings as early as the week of December 17th. Conceptual
design (30%) will be completed by early February with final design following
by the first part of May so that construction can be scheduled with the Siskiyou
Project in early July 2002.
As shown in the recommendations to Council, staff is proposing to
add this scope of work to the current design team for the Siskiyou project
headed by W&H Pacific. This allows a streamlined project and will link
some of the design concepts that are being utilized on the Boulevard. This
will also ensure timely completion of the project's design and coordination
during construction.
As a part of the agreement, ODOT is stipulating that the "City
agrees to enter into negotiations with ODOT to transfer jurisdiction of
OR
66 from MP 0+00 to MP 0.76
to the City. Such transfer shall occur
by way of a separate Abandonment Agreement between the parties." As
with most improvement projects, ODOT is moving toward having the local
jurisdiction (Cities and Counties) agree to take jurisdiction and all future
maintenance of district level highways so that ODOT can concentrate on their
primary Highway needs (I-5). None of the details have been discussed. Staff
will cooperate and in negotiating the agreement and ensure all of the maintenance
details are fair before bringing the proposal to Council for
consideration.
|
End of Document - Back to Top
December 11, 2001 Misc. Contracts &
Agreements
No. 20309 Key Number 12019; EA K0021
COOPERATIVE IMPROVEMENT AGREEMENT
Highway 66 Access Management Project
THIS AGREEMENT is made and entered into by and between THE STATE OF OREGON,
acting by and through its Department of Transportation, hereinafter referred
to as "ODOT; and City of Ashland, acting by and through its City Council,
hereinafter referred to as "City".
RECITALS
1. Green Springs Highway No. 21 (OR 66) is a part of the state highway
system under the jurisdiction and control of the Oregon Transportation
Commission.
2. By the authority granted in ORS 190.110, 366.770 and 366.775, ODOT
may enter into cooperative agreements with the counties and cities or units
of local government for the performance of work on certain types of improvement
projectswith the allocation of costs on terms and conditions mutually agreeable
to the contracting parties
3. By the authority granted in ORS 810.210, ODOT is authorized to
determine the character or type of traffic control devices to be used, and
to place or erect them upon state highways at places where ODOT deems necessary
for the safe and expeditious control of traffic. No traffic control devices
shall be erected, maintained, or operated upon any state highway by any authority
other than ODOT, except with its written approval. Traffic signal work on
this Project will conform to the current ODOT standards and specifications.
NOW THEREFORE, the premises being in general as stated in the foregoing
recitals, it is agreed by and between the parties hereto as follows:
TERMS OF AGREEMENT:
1. For the purpose of providing acceptable traffic patterns on public
highways, ODOT and City and plan and propose to design and construct access
management improvements which include, but are not limited to; concrete
driveways, sidewalks, raised median, striping, paving, signage, landscaping
and irrigation, hereinafter referred to as "Project". The location of
the Project is approximately as shown on the sketch map attached hereto,
marked Exhibit A, and by this reference made a part hereof.
2. The Project shall be conducted as a part of the Access Management
Bonding Program. The total estimated cost of the Project is $450,000. City
shall be responsible for any portion of the Project that is not covered by
State Access Management funds.
3. The term of this agreement shall begin on the date all required
signatures are obtained and shall terminate upon Project completion and final
payment. The Project shall be completed by and final billing submitted by
April 30, 2003.
CITY OBLIGATIONS
1. City shall design and construct Project to ODOT Highway Design
Manual standards, the AASHTO Policy on Geometric Design of Highways and Streets,
2001, and the 1999 Oregon Highway Plan for a District Level Highway, urban
standards, and all other appropriate ODOT standards.
2. City shall provide 3 copies of the plans and specifications to
ODOT's Area Manager for review and comment at least 6 weeks prior to the
date that bidding plans are due to be advertised.
3. City, or its consultant, shall conduct the necessary preliminary
engineering and design work required to produce final plans, specification
and cost estimates; obtain all required permits; arrange for all utility
relocations or reconstruction; perform all construction engineering, including
all required materials testing and quality documentation; prepare all bid
documents; provide project management services, and other necessary functions
for sole administration of the contract.
4. City shall advertise and award all contracts, and pay all contractor
costs.
5. City ensures that ODOT's contribution of Project costs, not to
exceed $450,000 will be applied to the Highway 66 Access Management Project
only. City shall be responsible for funding the remaining Project costs.
6. City shall keep accurate cost accounting records. City shall prepare
and submit progressive itemized billings to ODOT's Area Manager for review
and approval quarterly (every three months) during the Project timeframe,
with a final billing no later than April 30, 2003. Such billings shall reference
this IGA number, an invoice number, the Project's key number, and be in a
form acceptable to ODOT and documented in an easily verified manner.
7. City agrees to enter into negotiations with ODOT to transfer
jurisdiction of Greensprings Highway No. 21 (OR 66) from MP 0+00 to MP 0.76
from ODOT to the City. Such transfer shall occur by way of a separate Abandonment
Agreement between the parties.
8. City shall enter into and execute this agreement during a duly
authorized session of its City Council.
9. City agrees that should any environmental or land-use issues arise
at any time during the development or construction of the Project, ODOT may,
at its discretion and when exercised in good faith, suspend payments until
it is satisfied that the issue has been resolved. However, City may use its
own funds to continue the Project and shall be reimbursed once ODOT is satisfied
that the issue has been resolved.
10. City agrees and understands they or their consultant shall comply
with the Uniform Relocation Assistance and Real Property Acquisition Policy
Act of 1970, as amended, if right-of-way acquisition is necessary. Compliance
with said act is also required for any public right-of-way donated to the
City.
11. City or its consultant shall acquire all necessary rights-of-way
according to State Right of Way Manual, Chapter 13, Policy 13.200.
Certification of right-of-way acquisition work, or that no additional
right-of-way was needed must be made by the City (or on behalf of its consultant)
doing the work. The certification form shall be routed through the
Region Right of Way Office for co-signature and possible audit. If City elects
to have ODOT perform right-of-way functions, a separate agreement shall be
executed between the City and ODOT right-of-way, referencing this agreement
number.
12. City, its consultants or subcontractors, if any, and all employers
working under this agreement are subject employers under the Oregon Workers
Compensation Law and shall comply with ORS 656.017, which requires them to
provide workers' compensation coverage for all their subject workers, unless
such employers are exempt under ORS 656.126. City shall ensure that each
of its contractors complies with these requirements.
13. City acknowledges and agrees that ODOT, the Secretary of State's
Office of the State of Oregon, the federal government, and their duly authorized
representatives shall have access to the books, documents, papers, and records
of City which are directly pertinent to the specific agreement for the purpose
of making audit, examination, excerpts, and transcripts for a period of three
years after final payment. Copies of applicable records shall be made available
upon request. Payment for costs of copies is reimbursable by ODOT.
14. City shall comply with all federal, state, and local laws,
regulations, executive orders and ordinances applicable to the work under
this agreement, including, without limitation, the provisions of ORS
279.312,279.314,279.316, 279.320 and 279.555, which hereby are incorporated
by reference. Without limiting the generality of the foregoing, City expressly
agrees to comply with (i) Title VI of Civil Rights Act of 1964; (ii) Section
V of the Rehabilitation Act of 1973; (iii) the Americans with Disabilities
Act of 1990 and ORS 659.425; (iv) all regulations and administrative rules
established pursuant to the foregoing laws; and (v) all other applicable
requirements of federal and state civil rights and rehabilitation statutes,
rules and regulations.
ODOT OBLIGATIONS
1. ODOT shall, at its own expense, assign a liaison person to monitor
work performed. ODOT shall review all environmental documents, project plans,
specifications, and cost estimates prepared by City or its consultants within
20 working days of submittal by City and before advertisement of construction
bids.
2. After the completion of the Project and upon receipt of progressive
billings, ODOTshall reimburse City a sum in an amount not to exceed $450,000
for the actual costs of PE, right-of-way, CE and construction costs.
3. ODOT's assigned liaison person is Monte Grove, 200 Antelope Road,
White City, OR, 97503, 541-774-6353.
GENERAL PROVISIONS
1. ODOT and City agree that a mutual review of the construction plans
will be conducted prior to advertisement for construction bid proposals.
2. This agreement may be terminated by mutual written consent of both
parties.
3. ODOT may terminate this agreement effective upon delivery of written
notice to City, or at such later date as may be established by ODOT, under
any of the following conditions:
a. If City fails to provide services called for by this agreement
within the time specified herein or any extension thereof.
b. If City fails to perform any of the other provisions of this agreement,
or so fails to pursue the work as to endanger performanceof this agreement
in accordance with its terms, and after receipt of written notice from ODOT
fails to correct such failures within 10 days orsuch longer period as ODOT
may authorize.
c. If ODOT fails to receive funding, appropriations, limitations or
other expenditure authority at levels sufficient to pay for the work provided
inthe agreement.
d. If federal or state laws, regulations or guidelines are modified
or interpreted in such a way that either the work under this agreement is
prohibited or if ODOT is prohibited from paying for such work from the planned
funding source.
Any termination of this agreement shall not prejudice any rights or obligations
accrued to the parties prior to termination.
4. This agreement and attached exhibits constitute the entire agreement
between the parties on the subject matter hereof. There are no understandings,
agreements, orrepresentations, oral or written, not specified herein regarding
this agreement. No waiver, consent, modification or change of terms of this
agreement shall bind either party unless in writing and signed by both parties
and all necessary approvals have been obtained. Such waiver, consent,
modification or change, if made, shall be effective only in the specific
instance and for the specific purpose given. The failure of ODOT to enforce
any provision of this agreement shall not constitute a waiver by ODOT of
that or any other provision.
IN WITNESS WHEREOF, the parties hereto have set their hands and affixed
their seals as of the day and year hereinafter written.
This Project was approved by the Oregon Transportation Commission on January
10, 2001.
The Oregon Transportation Commission on March 18, 1999, approved Subdelegation
Order No. 2 in which the Director grants authority to the Executive Deputy
Director/Chief Engineer to approve and execute agreements over $75,000 when
the work is related to a project included in the Statewide Transportation
Improvement Program or is a line item in the approved biennial budget.
Signature Page:
| CITY OF ASHLAND, by and through its City
Council
Approved as to legal sufficiency by City Attorney
|
STATE OF OREGON, by and through its Department of
Transportation
Approval recommended by Region 3 Manager
Approved as to legal sufficiency by Assistant Attorney General
|
End of Document - Back to Top
|