City of Ashland, Oregon / City Recorder / City Council Information / Packet Archives / Year 2002 / 05/21 / Strawberry LID
Strawberry LID
[ Council Communication ] [
Map ]
Council Communication
| Title: |
Approval of Strawberry Lane Concept Design |
| Dept: |
Public Works Department |
| Date: |
May 21, 2002 |
| Submitted By: |
Paula Brown |
Reviewed
By:
........................ |
Greg Scoles, City Administrator |
| Synopsis: |
Council approved the formation of the Strawberry
Lane Local Improvement District (LID) at their regular meeting on November
20, 2001. During the discussion and public hearing, staff acknowledged that
the design would be brought back to the neighborhood during the 35% and again
at the 90% stages. On May 2, 2002, staff held an open house to provide the
opportunity for review of the 35% design. During that meeting, the primary
concern from the neighbors is the need for sidewalks. Sidewalks are shown
on the design, but the neighbors overwhelmingly requested that Council revisit
the need for sidewalks. |
| Recommendation: |
Staff has met the Council's policy to include sidewalks
in LIDs and new street design. The design shows that a sidewalk on one side
of the street along all of the street sections; Strawberry, Alnutt, Nutley,
Scenic and Westwood are possible and the impacts to the neighboring properties
are minimized. In some cases, the need for retaining walls is higher because
of a wider street/sidewalk cut into adjacent banks, and in other cases, there
is a need to acquire a small amount of additional right of way. However staff
supports the need for sidewalks to ensure the safety of pedestrians on these
fairly narrow street systems.
It is staff's recommendation to retain all of the sidewalks as shown
on this 35% design and proceed to the 90% and final design. It is further
recommended that the final design show a "heavy broom" finish on the concrete
sidewalks to provide additional roughness for these steep streets. |
| Fiscal Impact: |
The total project cost is estimated at $1,076,697
and includes the street work ($830,000) and storm drainage ($246,697). The
City's participation is $641,176. A rough estimate was calculated for the
sidewalk portion, which is estimated at $ 96,600. The cost could be higher
as the need for the retaining walls is reduced. It is estimated that the
total reduction if the sidewalks were removed from all of the areas would
be $125,000. If the sidewalks are removed from the project, there will be
an increase in design cost to redo these drawings, and a reduction in the
construction requirements. The overall "savings" would be approximately $
115,000. The City's portion of the costs would be reduced by that amount.
There would be no impact on the cost assessed to each homeowner as the City
is already subsidizing the difference between the full assessment (approximately
$10,441 per lot) and the LID cap of $4,140 per potential unit. |
| Background: |
After many years of discussion, the Strawberry LID
was formed in November 2001. The LID includes the upper end of Westwood,
Strawberry Lane down to Granite, Scenic (between Strawberry to Nutley), Alnutt
and Nutley above Scenic Drive. The design shows one way travel down the hill
on Strawberry between Alnutt and Granite, and one way travel on Alnutt from
Nutley to Strawberry. The LID includes participation form the developers
on the top of Strawberry, the City as we own property on the top of Strawberry
and also at the reservoir on Hitt Road, and the Parks Department, as they
also own parks land on the top of Strawberry.
Prior to forming the LID, staff held numerous meetings with the affected
property owners. Of primary concern was the need to retain trees and minimize
the negative impacts within a developed area. The design criteria were developed
during a walking tour of the site. All along, the neighbors in general have
objected to the need for sidewalks. There were suggestions that if there
was a need for sidewalks that they should meander around trees so that the
trees could be saved. The resulting drawing from Hammond Engineers (teaming
with Obec) shows the elimination of only three trees, some other vegetation
and overall, very limited impacts to the surrounding properties.
During the open house on May 2nd, the neighbors again expressed
significant concern with the need for sidewalks. They requested that the
sidewalks be eliminated and replaced with trails or pathways. Their concern
is with the width of the streets and with the urban feel of the neighborhood.
They have also expressed concern that the sidewalks would be too slippery
and would not allow adequate traction in the winter in icy conditions. Although
there have been other letters and prior emails, attached are two recent emails
from residents (the only ones received since the open house on May 2nd and
writing this staff report on May 15th), one in favor of sidewalks, one
opposed.
Current design shows sidewalks along one side of the road and are
summarized as:
-
Lower Strawberry (Granite to Alnutt) - 12' travel lane (one way down
from Alnutt to Granite) with 4' sidewalk on the south side. No trees are
threatened or scheduled to be removed.
-
Strawberry (Alnutt to Westwood) - 22' travel lane (two way traffic
parking on one side) with 4' sidewalk on one side. The current proposal shows
the sidewalk on the south side and crossing to the north past Hitt Road.
At the corner with Westwood, the sidewalk will meander to avoid the large
pine tree (on City property). No other trees are threatened or scheduled
to be removed.
-
Scenic (Strawberry to Nutley) - 20-22" travel lane (two way traffic
parking possible on one side in some locations) with 4' sidewalk on the east
side. Some of the sidewalk meanders around trees and there are some higher
(6-7 feet) retaining walls at the Strawberry Lane end. There is also a need
to obtain some right of way in one section. One tree threatened and no trees
are scheduled to be removed.
-
Alnutt (Nutley to Strawberry) - 12' travel lane (one way from Nutley
to Strawberry) with 4' sidewalk on the west side. There may be a need for
some right of way acquisition (minor if at all) and there will be a need
for retaining walls on the east side. The mailboxes at the end of Alnutt
at Nutley will need to be relocated. Three trees are threatened and scheduled
to be removed.
-
Nutley (Scenic to Alnutt) - 22' travel lane (two way parking on one
side) with 4-5' sidewalk on the south side. One tree is threatened and may
need to be removed.
-
Nutley (above Alnutt) - 18' travel lane (two way no parking) with
4' sidewalk on the south side. The sidewalk does meander to avoid four large
trees. No trees are threatened or scheduled to be removed.
-
Westwood - 22' travel lane (two way with parking on one side) and
5' sidewalks on the east side. The sidewalk meanders around a tree at the
end of the project limits and there may be a need to acquire additional right
of way at this location.
Additional Comments Addressed at the Open House:
During the open house there were a few details and suggestions / questions
brought up by the neighborhood - the first was the type of road surface.
Staff will continue to work with the consulting engineers to identify the
preferred surface texture to ensure there is adequate traction in the winter
months. Staff advised that during heavy icy conditions, the roads are so
steep that any surface is a challenge. Currently the best alternative is
an open asphalt mix that could have an imbedded slurry/chip. The concern
is that we ensure that if a chip seal is provided that the material is adequately
imbedded so that it does not cause more concerns with loose material on the
surface of the road. Staff will ensure that a recommendation is made at the
90% neighborhood meeting.
Some of the neighbors indicated a preference for meandering streets
and meandering sidewalks. In many areas the existing right of way is very
narrow and only 24-28 feet. Without gaining significant right of way, the
current location of the street allows the majority of the trees to be retained.
This would not be the case with any real "meandering" of the street. Similarly,
meandering standard 4 foot sidewalks would require additional right of way
and potentially the removal of some trees. Sidewalks, like roads are constructed
and have a gravel base so that they will not crack or fail. If a different
material (there were suggestions for gravel, sand or even bark or wood chips)
were used for sidewalks or pathways, they would be impossible to maintain
for regular use.
There was a concern with the narrow one way streets and the need for
a pull off if there are emergency vehicles. Staff will pose this concern
to the Fire Department and see if there is a need for mountable curbs in
some locations, or if there is space for a pull out. One down side with a
mountable curb is that on steep slopes in icy conditions, the vehicle could
roll over a mountable curb where it would be stopped with a standard curb
face.
One recommendation from a couple of the property owners was to close
lower Strawberry from Montview to Granite Street. Their concern was that
if lower Strawberry is used as an egress point for the new development that
there would be more accidents at the end of Strawberry at Granite. Staff
is concerned that this closure would, in effect, pose a cul-de-sac situation
and require out of direction travel. Staff does not recommend a change to
the current travel pattern and awaits further guidance from Council.
In all, the consultant has pulled together a very "doable" design
that incorporates the desires of the neighborhood to retain the trees and
provide a narrower sidewalk (4 foot instead of the standard 5 foot). Although
the design does urbanize the area and will definitely change the "feel" of
a more wooded rural area, those impacts have been minimized. The retaining
walls can be a pattern that is not a blank concrete wall and in some cases
could be a material that could be open for planting. The majority of the
retaining walls are less than 3 feet high and can be planted on the property
owner's side so that the construction material can be somewhat hidden and
softened. Staff is pleased with the design and with the ability to provide
sidewalks for the many walkers that both live in that area and enjoy walking
in that area.
|
End of Document - Back to Top
This map is available in PDF format. Click on the link below to view:
 | |
 |
The above document(s) are Adobe® Acrobat® PDF files and may be viewed using the free Adobe® Acrobat® Reader™. Most newer web browsers already contain the Adobe® Acrobat® Reader™ plug-in. However, if you need it, click on the "Get Acrobat® Reader™" icon to download it now.
|
|