City of Ashland, Oregon / City Recorder / City Council Information / Packet Archives / Year 2004 / 04/06 / ODOT Paving
ODOT Paving
[Council Communication]
[Attachments]
Council Communication
| Title: |
ODOT's Request to Approve Night Construction Work on the
Green Springs Highway (OR 66) within the City Limits (MP 0.8 to MP 1.99) |
| Dept: |
Public Works Department |
| Date: |
April 6, 2004 |
| Submitted By: |
Paula Brown |
| Approved By: |
Gino Grimaldi, City Administrator
|
| Synopsis: |
The Oregon Department of Transportation (ODOT) will be
soliciting bids in May for a pavement preservation project on the Green Springs
Highway (OR 66) within the City Limits (see attached map). This project includes
grading, drainage improvements, paving, signing and signal work. Although
it is ODOT's responsibility to meet all local ordinances, including Ashland's
Noise Ordinance, ODOT is seeking a variance to the ordinance in accordance
with AMC Section 9.08.170.C. ODOT is requesting the option to complete a
significant portion of the construction work at night throughout the timeframe
of the project; July 1, 2004 through September 15, 2004, which requires a
variance from the decibel levels in Section C. ODOT's request is attached.
It is likely that ODOT would continue to do some of the work during the day
such as adjusting inlets and concrete work (sidewalks and curbs) as these
items could be completed with short single lane closures. The majority of
the night work would be to accommodate longer lane closures and to avoid
the higher day time traffic volumes, for work items such as asphalt grinding,
paving, and possibly installing guardrail. |
| Recommendation: |
It is recommended that Council hold a public hearing to
hear concerns regarding ODOT's request to work at night. Pending the public
hearing and assuming no major concerns are voiced at the public hearing,
staff would recommend approval of ODOT's request with the following additional
conditions:
| 0 |
1) Night work hours should generally coincide with standard work hours
for the businesses such that there are no lane restrictions between 8 am
and 6 pm.
2) Contractor should maintain one operable travel lane in each direction
on the west side of I-5 during this night work period. Any night work on
the east side of I-5 must have adequate detours, signage and the contractor
must advise emergency dispatch of these closures.
3) The night work may not begin prior to July 12, 2004, and due to the 4th
of July holiday, it is the City's preference that work begin after July 7th
as opposed to July 1st as specified by ODOT.
4) NO night work shall be conducted between 9 pm Friday through 8 am Monday.
5) It is understood that there will be day time operations that may require
periods of intermittent lane and intersection closures. It is the contractor's
responsibility to follow safety precautions and notify emergency dispatch
during these periods. |
|
| Fiscal Impact: |
Although there is no tangible fiscal impact to the City
to allow night work, the intangible benefit to the community is positive
as this would minimize the traffic impacts during normal business operations
on OR66. |
| Background: |
The City's Municipal Code is very specific regarding the hours of allowable
noise. AMC Section 9.08.170.A states "No person shall make, assist in
making, continue, or cause to be made any loud, disturbing, or unnecessary
noise which either annoys, disturbs, injures, or endangers the comfort, repose,
health, safety, or peace of others." Construction activities are exempted
between the hours of 7am to 9pm (Section C.4); noises in excess of specific
decibel levels are considered public nuisances (Section C), yet the Council
can provide a variance (Section C.5).
This ODOT project is considered a pavement preservation project. As such,
project work will include grinding along the project area in some specific
locations, an asphalt pre-leveling course, some drainage inlet improvements,
new ADA accessible ramps, guardrail installation (primarily at the ramps
along I5 and along the curve at the transition prior to the E. Main Street
intersection), driveway approaches and final top lift paving throughout this
1.2 mile section. This project begins just south of the railroad tracks north
of Clay Street, and ends at the City limits between Dead Indian Memorial
Road and Oak Knoll Drive. Plans have not been included in this Council
Communication but are available in the City's engineering office and will
be available at the council meeting if there are specific questions of ODOT.
The grinding and paving portion of the roadwork will exceed "allowable" decibel
limits during the work period, but are exempted as "construction activities"
between the hours of 7am to 9pm (Section C.4). Strict compliance with the
Decibel Noise Standards would eliminate the ability to complete the grinding
and paving work. Strict compliance with the Decibel Noise Standards would
cause unusual and unreasonable hardship. If the work can proceed quickly
with less impact to businesses along this portion of OR Hwy 66, it is reasonable
for Council to grant the variance.
Should Council choose not to authorize and grant a variance for night time
work, this project will be completed during authorized construction hours
of 7:00 am to 9:00 pm. This will result in considerable impact on the businesses,
especially those on Hwy 66 between Clay Street and I-5. |
| Attachments: |
ODOT Paving
Attachments:
00 AMC 9.08.170
Unnecessary Noise
00 Map of the
area
00
ODOT Request letter dated February 10, 2004 |
End of Document - Back to Top
|