| Title: |
Modification of the 1995, 1999, 2000, 2001, 2002, and 2003
Annual Community Development Block Grant (CDBG) Action Plans for reallocation
of unexpended CDBG funds. |
| Dept: |
Community Development |
| Date: |
November 4, 2003 |
| Submitted By: |
Brandon Goldman, Assistant Planner
John McLaughlin, Director of Community Development |
Approved
By:
........................... |
Gino Grimaldi, City Administrator |
| Synopsis: |
In September, the City initiated the process of reallocating
past CDBG awards that have gone unexpended. The reallocation of past awards
requires modification of past years CDBG Action Plans through a public hearing
process.
There is concern that should the same delays in property acquisition persist
in the coming years that have occurred in the past, the city will be subject
to the Department of Housing and Urban Development's sanctions policy for
exceeding the 1.5x cap on accumulated carryover. If no projects are completed
prior to November 2004 the amount of potential reduction of future CDBG
allocations will be approximately $465,000. Thus it is imperative that the
City of Ashland find expeditious ways to expend the current carryover as
well as future allocations. Reallocation of previously unexpended CDBG awards
addresses this purpose. |
| Recommendation: |
Staff recommends approval of the Modification of prior years
CDBG Action Plans in accordance with Table 1 provided on page 3 of this
communication. |
| Fiscal Impact: |
No fiscal impact. Involves the reallocation of previously
awarded CDBG funds. |
| Background: |
The City Council reviewed the CDBG program and the issue of accumulated
carry-over on September 3rd, 2003 at a study session. The Housing Commission
held a special meeting on September 10th, 2003 to address the accumulated
CDBG funds and to receive project updates from the subrecipients, the Ashland
Community Land Trust and the Rogue Valley Community Development Corporation.
The Housing Commission recommended modifying the past CDBG Action Plans to
provide the Rogue Valley Community Development Corporation to combine the
2002 and 2003 CDBG awards to be applied to the purchase of the property located
at 2001 Siskiyou Blvd for the construction of 8-11 affordable housing units.
The Commission further recommended that RVCDC have until January 30th 2004
to expend the funds or they be recaptured and made available through a new
request for proposals. The Housing Commission recommended that the Ashland
Community Land Trust (ACLT) retain their $120,000 given confidence that their
project to develop 3 affordable housing units has made sufficient progress
in recent months. Lastly the Commission recommended that all other carryover
and unprogrammed funds should be reallocated through the 2004 Request for
Proposals process.
On September 16,2003 the City Council reviewed these recommendations and
directed Staff to propose the modification of past Action Plans accordingly.
RVCDC was awarded $21,000 toward pre-development expenses in 2002 related
to the affordable housing project proposed at the Lower Pines site. Of this
$21,000 RVCDC expended $7200 on the development of a Relocation Plan for
the residents of the trailer park. Although this activity was not completed,
the plan development was paid out of the CDBG program. RVCDC requested the
remaining $13,800 be applied toward predevelopment expenses on the Siskiyou
site. However as this project is no longer a tax-credit project, pre-development
costs are no longer an eligible use of CDBG funds. Therefore Staff has proposed
that these funds ($13,800) now be applied toward public facility improvements
at the Siskiyou site, as this would be an eligible use of CDBG funds.
The Public Works Department has begun soliciting bids for the accessibility
improvements to the Pioneer Hall Restrooms originally identified in the 2002
and 2003 Action Plans. This work will be undertaken during this program year
at a cost of approximately $15,000.
A table is provided (next page) that quantifies the amount of unexpended
funds from each Program Year and their proposed reallocation use. Note the
use of those funds identified to contribute to the 2004 CDBG Award is to
be determined by the City Council in review of proposals for use the 2004
CDBG Competitive Award. The selected use will be identified in the 2004 Annual
Action Plan. |
| Attachments: |
|
TABLE 1
Unexpended CDBG Funds to be reallocated
Proposed use to be final at adoption of 2004 Action Plan
| Program Year |
Project |
Unspent
Funds |
Reallocated
Amount |
Proposed use |
|
|
|
|
|
| 95-96 |
Unprogrammed |
$21,000 |
$21,000 |
2004 CDBG Award |
|
|
|
|
|
| 99-00 |
Accessibility |
$4,041 |
$4,041 |
2004 CDBG Award |
|
|
|
|
|
| 2000-2001 |
Accessibility |
$11,050 |
$11,050 |
2004 CDBG Award |
|
|
|
|
|
| 2001-2002 |
ACLT |
$120,000 |
0 |
ACLT Hersey Project
(This modification has been approved) |
|
Accessibility |
$11,500 |
$11,050 |
2004 CDBG Award |
|
|
|
|
|
| 2002-2003 |
RVCDC (Lower Pines) |
$168,750 |
$168,750 |
RVCDC (Siskiyou Property Acquisition) |
|
Accessibility |
$11,250 |
$11,250 |
Pioneer Hall Restrooms-ADA |
|
|
|
|
|
| 2003 |
RVCDC (Siskiyou Property) |
$193,000 |
0 |
RVCDC (Siskiyou Property Acquisition) |
|
RVCDC (Predevelopment costs) |
$13,800 |
$13,800 |
RVCDC (Siskiyou Property Public Facilities) |
|
admin (6 mos overlap) |
$25,605 |
$25,605 |
2004 CDBG Award |
|
accessibility |
$12,800 |
$3,750 |
Pioneer Hall Restrooms-ADA |
|
accessibility |
|
$9050 |
2004 CDBG Award |