Council Communication
| Title: |
Adoption of a Resolution Setting a Public Hearing
for the Final Assessment of three Local Improvement Districts: 1) Central
Avenue Improvements; 2) Penny Drive / Palmer Road Improvements; and 3) Helman
Street Improvements |
| Dept: |
Public Works Department |
| Date: |
July 15, 2003 |
| Submitted By: |
Paula Brown |
Approved
By:
........................... |
Gino Grimaldi, City Administrator |
| Synopsis: |
Attached are three project summaries and the resolutions
forming the three Local Improvement Districts (LID) for improvements to:
1) Central Avenue; 2) Penny Drive / Palmer Road; and 3) Helman Street Sidewalk.
Council action to set a public hearing to hear any objections to the final
assessments is required under the Ashland Municipal Code as one of the final
steps in the process to levy assessments to lots within each LID. The Central
Avenue LID was established on June 15, 1999 by the City Council prior to
completing the construction in 2000-01. The Penny Drive / Palmer Road LID
was formed by Council on December 22, 1999 and improvements were completed
in 2000. Council formed the Helman Street Sidewalk LID on October 3, 2001
and although the majority of the work was completed in 2001, the railroad
crossings were just recently completed. All three projects are now fully
completed and closed out so that final assessments can be appropriately charged
to the property owners. |
| Recommendation: |
Staff recommends that Council adopt the attached
resolution to establish a public hearing for 7:00 p.m., August 19, 2003,
to hear and consider objectives to the proposed final assessments for the
lots within the three LIDs: 1) Central Avenue; 2) Penny Drive / Palmer Road;
and 3) Helman Street Sidewalk. |
| Fiscal Impact: |
Each of the three LIDs has been completed and a detailed
cost analysis for each project is attached. Project costs are summarized
on the following page. |
| Background: |
Summary of Project Cost Estimates and Actual Costs
|
Summary of Project
Cost Estimates and Actual Costs
Resolution
Setting Public Hearing
Final Costs
for Central/Penny/Palmer/Helman LID's
These documents are available in PDF format. To view the document on
your computer, please click on the link below. The Adobe reader program
will open in a new browser window. Please use the browser's "Zoom"
feature to adjust the size of the text for comfortable reading.
|