| Title: |
Resolution increasing Electric rates in July
2003 |
| Dept: |
Electric & Telecommunication, Finance |
| Date: |
May 6, 2003 |
| Submitted By: |
Dick Wanderscheid, Lee Tuneberg |
Approved
By:
........................... |
Gino Grimaldi, City Administrator |
| Synopsis: |
Rising health care and PERS costs, electric personnel
returning to the electric utility from AFN, increased BPA transmission and
power costs require an electric rate increase. The rate model indicates the
need to increase our rates by at least 7.5%, and increase the BPA surcharge
from 16% to 20.8%, to meet the revenue requirements for the Electric
Utility. |
| Recommendation: |
Staff recommends the Council approve the Electric
Rate Resolution that increases electric rates by 7.5% and the BPA surcharge
from 16% to 20.8%. This would result in an overall increase of about 11%
in electric bills. |
| Fiscal Impact: |
This rate increase will generate about $659,000 of
additional electric rate revenue and $345,071 in additional surcharge
revenue.
For a residential customer that used 900 kWh's per month this would
translate in the electric bill (not including the tax) increasing from $47.01
to $50.54. Their surcharge would increase from $5.54 to $7.21
For a.commercial customer that used 3200kWh's of electricity per
month their bill for both energy and demand (not including the tax) would
increase from $204.41 to $220.21. Their BPA Surcharge would increase from
$51.21 to $55.05. |
| Background: |
The City last raised the base electric rates by 6%
and increased the BPA surcharge from 10% to 16% on July 1, 2002. The Council
approved the Rate Resolution on May 21, 2002. At that time we informed the
Council that because BPA rates were not known, this increase was a "best
guess" and actual rates would be analyzed and we would return to the Council
in October for an adjustment to the BPA surcharge if necessary.
On December 3, 2002, staff returned to the Council to report that
BPA Load Based Cost Recovery Adjustment Clause (LBCRAC),which covers BPA's
costs of purchasing additional power to meet their contracted electric loads
and Financial Based Cost Recovery Adjustment Clause (FBCRAC), which is triggered
if BPA's accumulated net revenue falls a preset threshold were only a little
higher than anticipated. Because BPA had decided not to impose the Safety
Net Cost Recovery Adjustment Clause (SNCRAC), which triggers if there is
less than a 50% chance of making their scheduled Treasury payment until October
of 2004, we recommended that no additional increase in our rates would be
required in October 2003. At this meeting staff informed the Council we would
be running the City's electric rate model during the late Winter and early
Spring using actual BPA billing data and actual electric loads to analyze
the status of the electric fund.
This has been accomplished and what the model showed was that the
actual BPA power bills appear to be about $400,000 more than originally estimated
necessitating a transfer of appropriation in this budget year to cover these
higher costs.
Before BPA implemented the cost Recovery Adjustment Clauses, the city's
wholesale power bill in 2001 was $ 4,526,894. The budgeted amount for FY
03-04 is $5,801,300 or $1,274,406 more than pre surcharge rates.
When the City became aware that the rates were going to drastically
increase, the council decided to use the surcharge concept to pay these higher
costs. The surcharge was exempted from the city's Electric User Tax to reduce
the impact on overall electric bills.
The current BPA surcharge of 16% collects $1,008,529. Increasing the
surcharge to 20.8% will result in an additional $345,071 for a total of
$1,353,600 in total surcharge revenue in FY 03-04. This is a little higher
than the amount of the projected wholesale power increases caused by BPA's
CRAC's.
Other costs in the utility are also increasing. Increases in health
care and PERS, and Electric personnel returning to the utility from AFN
construction duties, results in an increase of $222,300. Transmission fees
from BPA have increased by $60,814. Capitol spending has increased by 1.8%
or $10,000. Franchise fees are up by $46,800 and Central Service Charges
are also increasing by about $90,000. This coupled with the fact that our
ending fund balance target is only close to the target if our contingency
goes unspent, requires this general rate increase. The 7.5% rate increase
will help to cover all of these increased costs and also bring our ending
fund balance closer in line with our policy.
BPA has also just started the process necessary to trigger the SNCRAC.
This process will conclude in June, but an actual rate increase would not
occur until October 2003.
The City's BPA surcharge already covers the LB CRAC and FB CRAC costs
and these costs have been projected by BPA over the remainder of the rate
period as follows:
| Year |
LB CRAC & FB CRAC % (BPA Surcharge) |
| 2002
2003
2004
2005
2006 |
43%
45.5%
39%
37%
40% |
Therefore, if the SN CRAC is higher than the 6.5% reduction in the
other CRAC's projected for October 2003 (BPA's FY 2004), we could see another
wholesale power increase from BPA. However, the actual amount of the SN CRAC
won't be known until August. If the SN CRAC is substantially higher than
6.5%, we would have to discuss an increase in the BPA surcharge for October
2004. Staff will keep the council informed, as new information becomes available
on this issue. |
Back to Top
RESOLUTION NO. 2003- _______
A RESOLUTION REVISING RATES FOR ELECTRIC SERVICE PURSUANT TO ASHLAND MUNICIPAL
CODE SECTION 14.16.030 AND REPEALING RESOLUTION 2002- 09.
THE CITY OF ASHLAND RESOLVES AS FOLLOWS:
SECTION 1. The electric rate schedules are increased 7.5% for rates
for electric service provided by the City Ashland effective with Cycle one
billings prepared on or after July 1, 2003 as per the attached rate tables.
SECTION 2. The City of Ashland adopts a 20.8% surcharge (increased
from 16.0%) on billings for electric usage in addition to charges specified
in Section 1 to help pay for wholesale rate increases on power supplied to
the City of Ashland by the Bonneville Power Administration effective with
Cycle one billings prepared on or after July 1, 2003. The new surcharge rate
is $0.00801/kwh.
SECTION 3. The surcharge revenue is not subject to the Electric Utility
Tax or included in the franchise fee calculation for General Fund Revenues.
SECTION 4. Three copies of this resolution shall be maintained in
the Office of the City Recorder.
SECTION 5. Classification of the fee. The fees specified in Section
1 and Section 2 of this resolution is classified as not subject to the limits
of Section 11b of Article XI of the Oregon Constitution (Ballot Measure 5).
SECTION 6. Resolution 2002-09 is repealed.
This resolution was read by title only in accordance with Ashland Municipal
Code §2.04.090 duly PASSED and ADOPTED this 6th day of May,
2003.
Barbara Christensen, City Recorder
SIGNED and APPROVED this 6th day of May, 2003.
Alan W. DeBoer, Mayor
Reviewed as to form:
Paul Nolte, City Attorney
Rate Tables are available in PDf format. Please click on the link below
to view these documents on your computer:
 | |
 |
The above document(s) are Adobe® Acrobat® PDF files and may be viewed using the free Adobe® Acrobat® Reader™. Most newer web browsers already contain the Adobe® Acrobat® Reader™ plug-in. However, if you need it, click on the "Get Acrobat® Reader™" icon to download it now.
|
|