City of Ashland, Oregon / City Recorder / City Council Information / Packet Archives / Year 2003 / 04/01 / CIP
CIP
[Council Communication] [Council
Memo] [Spreadsheet]
Council Communication
| Title: |
Update on FY03 Capital Improvements Program and Related
Council Goals |
| Dept: |
Public Works Department |
| Date: |
April 1, 2003 |
| Submitted By: |
Paula Brown |
Approved
By:
........................... |
Gino Grimaldi, City Administrator |
| Synopsis: |
One of the Council's FY03 Goals is to "maintain
the city's commitment to implementing the CIP". Specific projects were
identified as follows:
-
Begin construction of Fire Station No. 1 - Project will be complete
by July 2003
-
Complete construction of new office space for the Community Development
and Public Works Administration Departments (Hillah) - Project substantially
complete and Public Works and Planning staffs moved in October 2002
-
Complete the expansion of the Library - Project will be fully complete
in may 2003
-
Begin construction of the Siskiyou Blvd. and Ashland St. improvements
- Ashland Street was completed in December, and Siskiyou is ahead of
schedule
-
Begin design of sidewalks for Tolman Creek Road - Design is nearly
complete. Construction scheduled to start in May/Jun 2003.
Attached to this Council Communication are two items; the first is
a spreadsheet with a very brief description depicting the current progress
of each project that has either been designated for FY03 funding, or has
been worked on this year; and the second is a council memo summarizing the
progress and funding for the wastewater treatment plant. |
| Recommendation: |
This is an informational item only. |
| Fiscal Impact: |
The total impact of each project is shown on the
attached spreadsheet. Although most of these projects are still in progress,
many of the larger projects (Library, Hillah, Fire Station, Siskiyou, WWTP)
are completed or costs are well known. In general, if you look at the total
combined cost for FY03 and FY04, the estimated costs were about one million
dollars less than what is now anticipated as actual costs. This can best
be summarized with the additional costs of the Siskiyou projects. There have
been minor changes in many of the other projects. The Ashland Street Main
line water replacement cost went significantly over budget, but this project
was also increased in scope and had problems with utility conflicts, extra
construction materials and additional coordination with SOU. By comparison,
the Bridge Street Storm Drain project was significantly under budget and
allowed the Morton Street project to be completed by contract and encompassed
a larger area. |
| Background: |
The Capital Improvements Program is fairly aggressive
for FY03. There are 44 projects listed for FY03 funding, 37 of which are
managed by public works. I am very please with the activity we have had this
year as all but two of those projects have been started. |
End of Document - Back to Top
COUNCIL
MEMO
Subject: Update on Siskiyou Projects and Costs
Date: March 4, 2003
Submitted By: Paula Brown, Public Works Department
Synopsis:
The Wastewater Treatment Plant has been under construction since September
1998. By September 2003, five years later, the site will be complete and
"construction free" for at least a few years. Carollo Engineers has been
our design engineers and construction manager during this entire period,
and Slayden Construction has been on the site the entire time.
It is my pleasure to highlight our state-of-the-art facility. There is a
brand new pump station at Ashland Creek that receives as much as 80% of the
total waste stream and pumps that raw waste to the headworks. A new dual-train
Eimco oxidation ditch effectively and efficiently processes our waste. The
ultraviolet disinfection system is environmentally safe and provides a thorough
disinfection process. The clarifiers have been retrofitted and a new one
added for capacity. The membrane facility is the first in Oregon and cleans
the final wastewater to better than the 0.08 mg/l phosphorous standard. Our
biosolids are processed through the Waste Activated Sludge system and will
go directly to the storage tank and then be dewatered in the centrifuges.
Provisions have been made to utilize the storage tank as a lime mixing facility
in the event that Ashland chooses to make a Class A sludge in the future.
Staff is working on the final hurdle with the temperature management plan,
which will devise the best way to meet the new TMDL for Bear Creek.
Recommendation:
This is an informational item only.
Fiscal Impact:
The City requested and received a total of $23,920,068 in Clean Water State
Revolving Fund Loan dollars from the department of Environmental Quality.
The City has used the initial allocation and has begun loan repayment. The
final $500,000 loan addition for the biosolids/dewatering facility has not
been reimbursed by DEQ.
The total cost, including all of the City's additional costs for the off-site
design, land acquisition and the wetlands demonstration facility is $33,616,000
as of February 4, 2003. The details are shown on the attached Summary of
facilities Costs and are categorized as:
Original On-Site Process Improvements
Aquionics UV Purchase
Process Improvement Change Orders
Ashland Creek Pump Station
Interim Solids Improvements (plus Ashbrook belt press)
Membrane Facility (plus Zenon membrane equipment)
Biosolids and Dewatering Facility (includes centrifuges)
Engineering and Construction Management (Carollo)
Ashland Land purchase, Wetlands, Permits (est)
TOTAL PROJECT |
$ 12,374,000
349,000
1,055,674
1,136,000
1,480,574
6,451,575
3,737,224
5,561,114
1,820,000
$ 33,616,161 |
Construction Completion Milestones:
-
The Construction Contract was awarded to Slayden Construction on August 4,
1998. Formal Notice-to-Proceed on the Ashland Wastewater Treatment Plant
Process Improvements Project was effective September 8, 1998.
-
Conversion from chlorine to ultraviolet disinfection was completed on March
1, 1999. Slayden met the interim milestone of 175 days to make this conversion
and the Aquionics UV Facility was considered fully operational.
-
City staff began to pump WAS from the existing plant into that basin No.
2 to utilize it for sludge storage and as an aerobic digester as the existing
digester was demolished. Oxidation Ditch No. 2 and the EIMCO equipment within
that side of the basin were considered to have reached Substantial Completion
as of March 3, 2000. The remaining Phase 1 facilities were considered to
have reached Substantial Completion as of July 31, 2000. Start-up and evaluation
of the controls and instrumentation for the Phase 1 Process Improvements
was completed On August 25, 2000.
-
The new Ashland Creek Pump Station and the pumping equipment and controls
for that facility are considered to have reached Substantial Completion as
of April 27, 2000.
-
The Operations Building reached completion on May 8, 2001, with the remaining
process improvements (Phase I) completed on June 20, 2001.
-
The Membrane Facility was operational as required on May 1, 2002, and we
completed start-up testing and debugging through July. The actual "substantial
completion" date for the Membrane Facility was July 31, 2002. We met the
phosphorous limitations of 0.08 mg/l through the dry weather months and the
system worked well. We have a minor problem with the alum pumps and full
automation and are working with Carollo Engineers and Slayden to correct
this prior to start-up in April. We plan to have the membrane facility start-up
each year the first week of April so that we can have all of the chemical
doses and backwash cycles in perfect shape by May 1st each year. The membrane
technology is great and provides exceptionally clean water. We meet all permit
limits and are actually providing better than required effluent quality for
the BOD and Suspended Solids requirements.
-
We are on schedule for completion of the final phase for the Dewatering /
Centrifuge Building and should be completed by May 2003. Once that facility
is on line, the contractor will dismantle the temporary belt-press building,
remove construction site trailers and complete final fencing and landscaping.
Slayden's plan is too complete this work and be off the site by late August.
-
We hope to have a real date for the open house to celebrate our successful
partnership not only with DEQ, but also with our community and show appreciation
for their extended patience for the past 5 years. We are planning to schedule
the open house in late July / early August as the remaining site work should
be completed.
The Capital Improvements Programs spreadsheet is
available in PDF format. To view this spreadsheet on your computer,
please click on the link below:
 | |
 |
The above document(s) are Adobe® Acrobat® PDF files and may be viewed using the free Adobe® Acrobat® Reader™. Most newer web browsers already contain the Adobe® Acrobat® Reader™ plug-in. However, if you need it, click on the "Get Acrobat® Reader™" icon to download it now.
|
|