City of Ashland - Home
Home Mayor & Council Departments Commissions & Committees Contact


 
LINE

 
LINE
 
LINE
 
LINE
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
*
*
 
LINE
 
LINE
 
LINE
 
LINE

Notify me by Email
 

City of Ashland, Oregon / City Recorder / City Council Information / Packet Archives / Year 2003 / 03/04 / TAP

TAP

Council Communication
Title: Preliminary Engineering for Talent Ashland Phoenix (TAP) Intertie Pipeline for Future Construction of the line from Talent to Ashland
Dept: Public Works Department
Date: March 4, 2003
Submitted By: Paula Brown
Approved By:
...........................
Gino Grimaldi, City Administrator

Synopsis: Based on the Council's decision in December 1998, staff has moved forward on Ashland's commitment to participate with the cities of Talent and Phoenix in the design and construction of the TAP Intertie water pipeline (24-inch line) to the City of Talent. In addition, Council asked staff to review the following:
  • Lost Creek Water Rights: Evaluate the strategy for the purchase of these water rights; timing, quantity, etc.
  • Review the process of changing the City's Talent Irrigation District (TID) water rights from the City's "Imperatrice Property" for beneficial use within the City;
  • Begin discussions with the City of Talent regarding their TID municipal water rights and future use of those rights; and
  • Continue with conservation programs in an effort to meet the goals for 20% peak day summer time reductions.

Council's Goal Setting held February 8, 2003, renewed interest in developing the preliminary engineering, securing easements for the pipeline and identifying other needs for this future project. This item is being brought to Council to provide an update on the TAP process, water rights purchase, and the future needs for the City of Ashland. This item will also provide options and a recommendation on the next steps in the process.

Water has been, and will continue to be, a concern for the Rogue Valley. The City of Ashland will have intermittent drought years followed by periods of sufficient water for the foreseeable planning period. However, as we look at reasonable projections for growth, water use and successful conservation programs, staff's concerns for adequate water supply reflect the community's desires. Planning for adequate water supply lead staff to recommend that we develop a funding mechanism so that construction of the TAP Pipeline and ancillary improvements and connections to the City's distribution system can be completed by June 2008.

Recommendation: Staff's recommends that Council direct staff to develop and circulate a request for proposals for preliminary engineering analysis for the continuation of the TAP Pipeline from Talent to Ashland, and complete the engineering analysis by June 2004.
Fiscal Impact: The preliminary engineering costs are anticipated to be $35,000 - 50,000 and will be added to the FY04 budget. Any recommended right-of-way or additional engineering will be in future year's budget.

As a reminder, the following summarizes the total anticipated costs of the project:

Paid Future costs
TAP Pipeline Construction Medford to Talent (2002)
Purchase Water Rights (2002)

$1,450,000
931,000

Engineering
   Preliminary (now)
   Final

Future Connection of TAP from Talent to Ashland (incl engr)
Future SDCs to Medford Water Commission (assumed)


$ 50,000
300,000
2,000,000
1,500,000

Future Ashland Pump Station
Future Ashland Distribution System Upgrades
Additional Lost Creek Water (increased costs)

750,000
1,000,000
400,000

TOTAL Costs:
Paid to date:

8,381,000
2,31,000

Total Future Costs:

$6,000,000

These costs could be funded through a combination of funding sources including
Water Supply SDCs

Water Distribution SDCs
Water Rates

approximately 75% of TAP Pipeline, 100% water rights and 75% SDCs
approximately 75% PS and Dist upgrades
approximately


3,287,500
1,312,500
1,400,000

The Water Enterprise fund has a significant list of necessary upgrades in the next 3-5 years. Staff will develop a request for proposals for preliminary engineering. The scope of work will include pipeline alignment, easement requirements, initial placement for the receiving well and any initial engineering needs for the link to the City's distribution system. Staff will ask for alternative alignments to ensure nothing is overlooked even though it is likely that the pipeline will continue down Hwy 99. Staff anticipates the need for up to a 1 million-gallon distribution reservoir and thought is to use that as the receiving well. Placement of that reservoir is in question and the scope of work will include that review. The preliminary engineering study will get underway in June/July 2003 and will be completed within 9 months. Staff will periodically bring updates to council for their input and review of necessary decisions. Staff continues to recommendation Council look at funding the TAP Pipeline construction in 2008/09.

Background: The following information has been provide in the past, but has been updated as of February 2003.

Review of the Water Master Plan Assumptions and Recommendations

Carollo Engineers was hired in July 1998 to assist the City in developing a long-term comprehensive water supply study. While the City has an adequate water supply during non-drought years, the construction of the TAP Intertie pipeline from Medford to Talent required Ashland's decision to participate in the construction. The Master Plan looked at the City's supply and demand for water through the year 2050 (Technical Memorandum #1). The conclusions indicate that the City would not be able to provide adequate supply during severe drought conditions as Reeder Reservoir is undersized. Aggressive summer conservation could theoretically achieve a 20% reduction, however, the recommendation is that the City implement a voluntary curtailment program that targets a 10% reduction during the high use summer months - every year. Mandatory curtailment would be used to achieve the additional 10% (total 20%) reductions during sever drought conditions. The estimated supply needs for 2050 required alleviating a 430 million gallon deficit.

The Comprehensive Master Plan evaluated and discussed several different options. The TAP pipeline was the only "stand-alone" alternative that could supply the City with the necessary 430 million gallon deficit that is projected (technical memorandum #2). Carollo summarized the findings and recommendations in Technical Memorandum #3, which is attached to this report. Although this document has a published date of January 1999, these recommendations were the basis of Council's decision in December 1998 to cooperate in the construction of the TAP Pipeline and evaluate other water supply needs.

The timing of the construction of the TAP Pipeline to Ashland and overcoming even short-term deficits are highly dependent upon drought conditions. The reports suggest that with "…aggressive summer conservation, the City can theoretically reduce the overall [water supply] deficit through the year 2020. "However, demand reduction conservation would need to be achieved every year during the highest demand months to adequately protect against unanticipated drought. Demand reduction by summer conservation alone is therefore not considered a suitable planning strategy for deficit reduction." The amount of projected deficit is a strong function of projected population growth and other factors including drought conditions. The year 2016 has been used as a planning target for overcoming the additional growth related deficit and completion of the TAP Pipeline to Ashland.

Update on the TAP Intertie Project

The TAP Intertie Project includes a 24-inch pipeline from Medford to Talent. The cities of Talent, Ashland and Phoenix, hired Montgomery Watson (MW - now Montgomery Watson Harza - MWH) Engineering to complete the final engineering design and also to provide construction management services during the construction of the TAP Intertie pipeline. The Rogue Valley Council of Governments (RVCOG) assisted in contract oversight during construction and will continue to act as the coordinator for the three cities during the operation of the pipeline.

Construction is complete and includes the pipeline along Hwy 99, a Regional Pump Station at Belknap and Hwy 99, telemetry links with the City of Medford, Talent and Phoenix (and eventually will include Ashland). Both Talent and Phoenix have has ancillary water system improvements designed and constructed as a part of their funding through a combination grant and loan program through the Rural Development that are not specifically part of the TAP Intertie costs.

Construction Costs to Date: The engineer's estimate for the construction work was $10,660,060. James W. Fowler's bid (September 2000) for the work was $8,968,817 and there have been change orders to increase that cost to $9,260,255. The City of Ashland participated in only three portions of the project including the project mobilization, the 24" diameter pipeline from Medford to Talent, and the Regional Pump Station. The total construction estimate for those portions was $5,410,243 and the flow-based portion for Ashland is 19.39% or $1,049,046. The City of Ashland participated in 5 of the 13 change orders (the other 8 were specific to Talent or Phoenix), which increased the total cost to $5,442,636, with Ashland's portion totaling $1,058,256. James Fowler did an excellent job with keeping the costs within the estimate, and the total change orders on the primary three-city portion were less than 1%. The Capital Improvements Budget allowed for $1,245,000 for the TAP construction and engineering / construction management costs.

Non-Construction Costs to Date: Ashland has participated in the MWH design, construction management, and bidding services at an authorized contract cost of $137,737, RVCOG administrative oversight and management services are authorized to a total of $30,000 (not fully expended and will actually continue after the construction phase of the project), and pump station land acquisition costs of $12,000. The total Ashland participation estimate of these non-construction or land acquisition costs is just under $180,000. The annual costs for RVCOG are expected to be less than $8,000 for Ashland's portion.

Lost Creek Water Rights

Based upon Carollo Engineer's evaluation for the Comprehensive Water Master Plan, the total annual deficit during a drought year for the planning horizon of the year 2050, with recommended aggressive conservation and curtailment in drought year, and with some reallocation of water rights, is 430 million gallons (Technical Memorandum #1). Carollo recommended obtaining 450 million gallons (or 1380 acre-feet) of water from Lost Creek Lake at a cost of $674 per acre/foot or a total of $931,000. The City formally initiated the process and purchased water rights for a total of $931,000 in June 2001. Subsequent to that authorization, the Corps of Engineers has discovered an error in their interest calculations so that the amount of water the City purchased is significantly less than anticipated. For the $931,000, the City has purchased approximately 920 acre feet of water. The details of this difference are still being worked out with the Corps. The difference in needed water rights will be budgeted for FY03 purchase.

TID Water Rights Reallocation - "Imperatrice Property"

During the water master planning efforts, there was a proposal to look at the City's water rights on the newly purchased Imperatrice Property. Initial intentions were to use treated effluent as the irrigation source on the City's "Imperatrice" Property and explore the possibility of using a portion of the TID water rights currently assigned to that property for irrigation. However, as the City has decided not to irrigate the land with treated effluent, the water rights have remained on the property. The City was able to shift a portion of the water rights to other City use late in the summer of 2001 to help offset the City's need for additional allocation for TID supplemented drinking water. This was a one-time allocation.

At one time, there was discussion by the Council to explore the possibility of providing "leased" water for in-stream beneficial use to replace a portion of the wastewater treatment plant effluent. The ability to lease the water for in-stream use to meet a targeted flow is possible, but may not be possible after the end of irrigation season when the creek flows are the lowest. This issue was discussed with TID and the State Water Master without much possibility of success and would most likely require the Federal Bureau of Reclamation (USBOR) approval.

Conservation Programs to meet the Goals for 20% Peak Day Summer Time Reductions

The Comprehensive Water Master Plan adopted by the Council recommended continued efforts to achieving conservation goals. The water deficit numbers used in planning for the water need in the future depended upon achieving a 20% reduction in water use in the summer. With this past summer's drought conditions, the City felt the impact of mandated water curtailment and the initial impacts of a significant water conservation program. There were many complaints and concerns as the City achieved only a 10.5% reduction during the summer months. A 20% conservation program is extremely aggressive and may not be attainable several years in a row without additional measures.

Water Supply and Demand

Reeder Reservoir is relatively small as the maximum storage behind the dam is 860 acre-feet or 280 million gallons of raw water with the overflow weirs in place. Reeder Reservoir is fed from snow melt and watershed rain runoff from Mount Ashland. Typically, the reservoir fills to the top and reaches capacity in April, stays full and spills over the overflow weirs at the dam through to the end of May, and then the water level behind the dam slowly starts to fall until the rains begin again usually sometime in October. Theoretical drawdown of the reservoir begins the first of June and goes to "empty" in March. The reservoir never reaches "empty" because of rains that usually start in October. The predicted 50% reservoir level is October 15th. Anytime after October 15th without rains and with the reservoir at or below 50% would cause concern for water supply.

Water use in the summer months is highly dependant upon weather conditions; the warmer the weather, the higher the use. When the late spring / early summer temperatures are in the 70s, the averaging use is 4-4.5 million gallons a day (mgd). With temperatures in the 80s, water use reaches 5-5.5 mgd, and with temperatures in the 90s, average water use is 6-6.5 mgd. Peak temperatures result in peak water use of about 7.5 mgd. We have had days in prior years with use as high as 8 mgd. The 2001 drought year showed that our community was willing to monitor their use. During the voluntary conservation periods, the average use in August dropped to 5.3 mgd. During September, the month of mandatory curtailment, the average use dropped to 4.1 mgd. As soon as temperatures cooled off in mid October, the average use dropped to 2.0-2.4 and stayed in that range.

TID Supplement: The City has an alternate water source to draw upon through an agreement for 769 acre-feet of perpetual domestic water rights from the Talent Irrigation District (TID). During drought years or less than average water years, the City will use TID to augment water storage in Reeder Reservoir.

Discussions with the City of Talent regarding their TID Municipal Water Rights

The City of Talent relinquished their 300 acre-feet of stored water rights within the TID system and suggested that Ashland pursue those rights. Staff has made contact with personnel at the Bureau of Reclamation for an option on those rights and will also discuss this option with Oregon's Water Rights personnel. As the City has lost the rights to prior 1966 TID water, this might be an option to regain a good portion of those M&I rights.

Renegotiating the 1966 TID Water Use Agreement

Staff has had no success, but continues discussions with TID, the Bureau of Reclamation (BOR) and the State Water Master on the re-negotiation and renewal of our 1966 Agreement for 795 acre-feet of stored water. There are questions regarding the type of water (whether it is specified irrigation or M&I), the stored rights (from which initial allocation), and the ability to use the water outside of the regular irrigation season that complicate the renewal of the agreement. Ashland is asking for a determination on the type of water rights and prefers they be specified as domestic or M&I so that there is no question regarding use of the water. There are several initial permits that TID has for the Howard Prairie/Hyatt Lake water that need to be reviewed. BOR has indicated a need for City funding to review and make decisions on all of these permits. Initial agreements for acquiring the right to stored water between TID and the City were made in 1923, prior to the formation of the BOR.

With the Klamath Tribes now formally challenging the water diversions, it seems even more unlikely that the City will be successful in re-negotiating these 1966 agreements and rights. It may be more prudent to drop these discussions if the 300 acre-feet of Talent water rights can be secured and ask that the Bureau look at stream flow augmentation.



End of Document - Back to Top



 

printer friendly version Printer friendly version

If you have questions regarding the site, please contact the webmaster.
Terms of Use | Built using Project A's Site-in-a-Box ©2012

View Mobile Site

News Calendar Agendas NewsCalendarAgendasFacebook Twitter